SCMA 350 Chapter 1 Questions with Correct
Answers
Projects often require tradeoffs among all of the following EXCEPT:
a. scope
b. cost
c. schedule
d. programs
Programs
Which of the following examples is NOT a typical or appropriate situation to employ
project management?
a. improving a soldering process in an assembly line
b. processing deposits and withdrawals in a bank
c. installing a new accounting application on a server
d. developing a new medical device for use by clinics
processing deposits and withdrawals in a bank
Typically, a steering team or leadership team is responsible for all of the following
project related roles EXCEPT:
a. selecting, prioritizing and resourcing projects
b. standardizing project-related governance processes to facilitate sharing of
methodologies, tools & techniques
c. ensuring accurate progress is reported and adjustments made
d. evaluating projects and portfolios midstream to ensure they produce expected results
Answers
Projects often require tradeoffs among all of the following EXCEPT:
a. scope
b. cost
c. schedule
d. programs
Programs
Which of the following examples is NOT a typical or appropriate situation to employ
project management?
a. improving a soldering process in an assembly line
b. processing deposits and withdrawals in a bank
c. installing a new accounting application on a server
d. developing a new medical device for use by clinics
processing deposits and withdrawals in a bank
Typically, a steering team or leadership team is responsible for all of the following
project related roles EXCEPT:
a. selecting, prioritizing and resourcing projects
b. standardizing project-related governance processes to facilitate sharing of
methodologies, tools & techniques
c. ensuring accurate progress is reported and adjustments made
d. evaluating projects and portfolios midstream to ensure they produce expected results