1. A facility energy manager is developing a baseline for an Energy
Conservation Measure (ECM). Which approach is most appropriate for
establishing a reliable baseline?
A. Using the highest historical energy consumption month
B. Using a single day of peak load data
C. Using normalized historical utility data adjusted for weather and
occupancy
D. Using estimated energy consumption from equipment nameplates
Correct Answer: C
A baseline must reflect typical operating conditions and should be
normalized for key variables such as weather, occupancy, and
, production to ensure accurate comparison after ECM
implementation.
2. Which IPMVP option is most suitable for evaluating savings from a
whole-building retrofit?
A. Option A
B. Option B
C. Option C
D. Option D
Correct Answer: C
Option C evaluates whole-building energy use and is best for
comprehensive retrofits where multiple systems are affected.
3. A building installs a variable frequency drive (VFD) on a constant-
speed pump. What is the primary energy benefit?
A. Increased pump head pressure
B. Reduced motor efficiency at all speeds
C. Reduced energy consumption through speed control
D. Increased water flow rate
Correct Answer: C
VFDs reduce motor speed based on demand, significantly lowering
energy consumption due to affinity laws.
4. Which factor most directly influences HVAC cooling load in a
commercial building?
A. Window frame material only
, B. Outdoor air temperature and internal heat gains
C. Transformer efficiency
D. Pipe insulation thickness
Correct Answer: B
Cooling loads are primarily driven by external temperature
conditions and internal heat gains from occupants, lighting, and
equipment.
5. What is the main purpose of Measurement and Verification (M&V)?
A. To increase equipment efficiency
B. To confirm savings from implemented ECMs
C. To replace energy audits
D. To design new HVAC systems
Correct Answer: B
M&V verifies that projected energy savings from ECMs are actually
achieved and measurable.
6. Which system is most commonly targeted in energy efficiency projects
for large buildings?
A. Fire alarm system
B. Elevator communication system
C. HVAC system
D. Parking control system
Correct Answer: C
, HVAC systems typically account for the largest portion of building
energy use and are primary targets for efficiency improvements.
7. What is a key advantage of sub-metering in energy management?
A. Eliminates need for utility bills
B. Provides detailed energy use by end-use systems
C. Reduces equipment maintenance costs directly
D. Prevents system breakdowns
Correct Answer: B
Sub-metering allows detailed tracking of energy consumption by
individual systems or areas, improving analysis and targeting.
8. Which ECM would most likely reduce lighting energy consumption?
A. Increasing ballast size
B. Replacing incandescent bulbs with LEDs
C. Installing larger transformers
D. Increasing daylight obstruction
Correct Answer: B
LED lighting significantly reduces energy consumption compared to
incandescent lighting due to higher efficiency.
9. What is the primary purpose of benchmarking energy performance?
A. Designing HVAC systems
B. Comparing energy use against similar buildings or standards
C. Increasing electricity tariffs
D. Eliminating utility meters