DBIA Code of Conduct Enforcement Complete Exam Study Questions with 100% Correct Answers | Latest Version 1. Federal Government passed bond requiring payment and performance bonds on all public works, what year? - ANSWER Miller Act 1935 2. Bill directing A/E's selected on qualifications, what year? - ANSWER Brooks Bill 1972 3. Allows all federal agencies to utilize Design-Build. Prior to that no enabling legislation existed allowing Design-Build. - ANSWER Clinger Cohen Act/Defense Procurement Reform Act 1996 4. The level of quality that any average Design Professional would be able to perform given the circumstances. - ANSWER Standard of Care 5. Single point of responsibility for both design & construction is an attribute of what delivery method? - ANSWER Design Build 6. The process of checking milestones along the way for completeness. - ANSWER Substantiation 7. Owner requiring specific products or methods be instituted by DB team in order to achieve desired performance. - ANSWER Prescriptive 8. T/F Detailed estimating is the Building systems approach to estimating - ANSWER False 9. T/F feasibility estimate is cost model and establishes budget for project - ANSWER False 10. T/F key element of quality assurance is keeping communication lines open between owner and DB - ANSWER True 11. T/F in Design/cost relationship of DB, the constructor establishes design parameters for architect - ANSWER True 12. T/F trust is most important thing for DB - ANSWER False 13. DB estimating sequence where 15%-20% of design is completed - ANSWER Schematic estimating 14. Provides baseline budgets and schedules and list estimate trends - ANSWER Trend logs 15. Drawings and specs are approved by DOR and confirmed within budget - ANSWER Committed Design 16. What is NOT a design managers role? - ANSWER Coordinating owner design reviews and approvals 17. Who is responsible for ensuring quality assurance? - ANSWER Design Build Team 18. When programming and design is developed by DB entity - ANSWER Direct DB 19. Establishes that under DBB, owner is responsible for increased cost due to defective plans/specs - ANSWER Spearin Doctrine 20. Selection where qualitative aspects are scored out of 100 the divided by qualitative score - ANSWER Adjusted low bid 21. Slowest Project Delivery method, linear in nature, prescriptive (owner knows what they want), - ANSWER Design Bid Build 22. Project Delivery - Many contracts through Owner - ANSWER Multi Prime 23. Project Delivery method allowing the contractor to come on board very early in design for preconstruction services yet maintains separation between Designer and Builder contractually. - ANSWER CM at Risk 24. Fastest Project Delivery method, fast tracking possible overlapping design with construction utilizing incremental packages. - ANSWER Design Build 25. Procurement Method - Most Familiar - ANSWER Low Bid 26. Procurement Method - Common for A/E - ANSWER Negotiated (Qualifications Based) 27. Procurement Method - Qualifications and Price - ANSWER Best Value 28. Procurement Method - Direct - ANSWER Sole Source 29. Contract Format w/ agreed upon fixed price - ANSWER Lump Sum 30. Contract Format - contractor reimbursed for actual cost plus an agreed upon percentage - ANSWER Cost Plus Fee 31. Contract Format - Combines Cost-Plus & Lump-Sum, contractor reimbursed for actual cost plus a fee only up to a certain amount. - ANSWER GMP (Guaranteed Maximum Price) 32. Contract Format - cost per piece - ANSWER Unit Price 33. Contract Format - established cost/benchmark determined jointly by project team. - ANSWER Target Price 34. Successful Design Build requires _____ & _______ between participants - ANSWER Trust, Flexibility 35. Singular responsibility for both design & construction was first codified by ____ - ANSWER Hammurabi 36. Owner provided items such as 20% design or more and provides prescriptive specs at RFP. - ANSWER Bridging Documents 37. Owner is responsible for implied warranties in the sufficiency of the specifications. - ANSWER Spearin Doctrine

Voorbeeld van de inhoud

DBIA Code of Conduct Enforcement
Complete Exam Study Questions with
100% Correct Answers | Latest
Version

1. Federal Government passed bond requiring payment and performance bonds
on all public works, what year? - ANSWER Miller Act 1935


2. Bill directing A/E's selected on qualifications, what year? - ANSWER
Brooks Bill 1972


3. Allows all federal agencies to utilize Design-Build. Prior to that no enabling
legislation existed allowing Design-Build. - ANSWER Clinger Cohen
Act/Defense Procurement Reform Act 1996


4. The level of quality that any average Design Professional would be able to
perform given the circumstances. - ANSWER Standard of Care


5. Single point of responsibility for both design & construction is an attribute
of what delivery method? - ANSWER Design Build


6. The process of checking milestones along the way for completeness. -
ANSWER Substantiation


7. Owner requiring specific products or methods be instituted by DB team in
order to achieve desired performance. - ANSWER Prescriptive

,8. T/F Detailed estimating is the Building systems approach to estimating -
ANSWER False


9. T/F feasibility estimate is cost model and establishes budget for project -
ANSWER False


10.T/F key element of quality assurance is keeping communication lines open
between owner and DB - ANSWER True


11.T/F in Design/cost relationship of DB, the constructor establishes design
parameters for architect - ANSWER True


12.T/F trust is most important thing for DB - ANSWER False


13.DB estimating sequence where 15%-20% of design is completed -
ANSWER Schematic estimating


14.Provides baseline budgets and schedules and list estimate trends -
ANSWER Trend logs


15.Drawings and specs are approved by DOR and confirmed within budget -
ANSWER Committed Design


16.What is NOT a design managers role? - ANSWER Coordinating owner
design reviews and approvals

, 17.Who is responsible for ensuring quality assurance? - ANSWER Design
Build Team


18.When programming and design is developed by DB entity - ANSWER
Direct DB


19.Establishes that under DBB, owner is responsible for increased cost due to
defective plans/specs - ANSWER Spearin Doctrine
20.Selection where qualitative aspects are scored out of 100 the divided by
qualitative score - ANSWER Adjusted low bid


21.Slowest Project Delivery method, linear in nature, prescriptive (owner
knows what they want), - ANSWER Design Bid Build


22.Project Delivery - Many contracts through Owner - ANSWER Multi Prime


23.Project Delivery method allowing the contractor to come on board very early
in design for preconstruction services yet maintains separation between
Designer and Builder contractually. - ANSWER CM at Risk


24.Fastest Project Delivery method, fast tracking possible overlapping design
with construction utilizing incremental packages. - ANSWER Design Build


25.Procurement Method - Most Familiar - ANSWER Low Bid


26.Procurement Method - Common for A/E - ANSWER Negotiated
(Qualifications Based)


27.Procurement Method - Qualifications and Price - ANSWER Best Value

Documentinformatie

Geüpload op
19 juli 2026
Aantal pagina's
27
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden
$11.99

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kan je een ander document kiezen. Je kan het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Seller avatar
DrSammuel
5.0
(1)
Verkocht
7
Volgers
0
Items
917
Laatst verkocht
1 week geleden


Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via Bancontact, iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo eenvoudig kan het zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen