Who can best interpret Architect
Architectural drawings?
Who should sign architectural Architect
drawings?
You were commissioned to do Survey the location
a Master Plan. What should
you do first?
Responsibilities of an Full time supervision
Architect: When He/She
conducts the checking of
materials and works done it it
in adherence with the
specifications
How often does the Architect- As often as he/she wants
of-record visit the job site?
Specifications should be clear Sentence with double meaning
and easy to understand. What
must be avoided?
,The record tests of materials 5 years
and of concrete must be
preserved after the
completion of the project for a
t least?
After a change of use Certificate of occupancy
(renovation)of the building,
what should be secured?
A permit prior to the Building permit
commencement of a project
What are the qualifications of Filipino citizen, Graduate of Architecture,
someone who wishes to take Submitted the necessary requirements to
the licensure exam for PRC, (ALL OF THE ABOVE)
architects?
After how many days can a 15 days
contractor stop work if the
architect's approval for the
change of work is delayed?
An outline specification Schedule of materials and finishes
enumerating the type trade
names of materials to be used
and finishes is known as
Under PD 957 and BP 220, how 20
many units shall be the
maximum number of row
houses per block/cluster?
, Under BP 220, the maximum 2.00 meters
length of a block is 400
meters. However, Block
lengths exceeding 250 meters
should be provided with an
alley approximately ay
midlength. How wide is the
alley?
Under BP 220. it shall have a Pathwalk
width of 3.00 meters intended
only to provide pedestrian
access to property for
socialized housing projects. It
shall have a maximum length
of 60 meters
Under PD 957, what is the 4
minimum lot frontage for row
houses?
Under BP220, what is the 3.5 Meters
minimum lot frontage for
socialized row houses?
Which of the following is not Yard
part of the RROW?
What is the minimum RROW Verify Answer
access to an Interior lot?
and Answers with Verified Solutions | Latest
Updated 2026
Who can best interpret Architect
Architectural drawings?
Who should sign architectural Architect
drawings?
You were commissioned to do Survey the location
a Master Plan. What should
you do first?
Responsibilities of an Full time supervision
Architect: When He/She
conducts the checking of
materials and works done it it
in adherence with the
specifications
How often does the Architect- As often as he/she wants
of-record visit the job site?
Specifications should be clear Sentence with double meaning
and easy to understand. What
must be avoided?
,The record tests of materials 5 years
and of concrete must be
preserved after the
completion of the project for a
t least?
After a change of use Certificate of occupancy
(renovation)of the building,
what should be secured?
A permit prior to the Building permit
commencement of a project
What are the qualifications of Filipino citizen, Graduate of Architecture,
someone who wishes to take Submitted the necessary requirements to
the licensure exam for PRC, (ALL OF THE ABOVE)
architects?
After how many days can a 15 days
contractor stop work if the
architect's approval for the
change of work is delayed?
An outline specification Schedule of materials and finishes
enumerating the type trade
names of materials to be used
and finishes is known as
Under PD 957 and BP 220, how 20
many units shall be the
maximum number of row
houses per block/cluster?
, Under BP 220, the maximum 2.00 meters
length of a block is 400
meters. However, Block
lengths exceeding 250 meters
should be provided with an
alley approximately ay
midlength. How wide is the
alley?
Under BP 220. it shall have a Pathwalk
width of 3.00 meters intended
only to provide pedestrian
access to property for
socialized housing projects. It
shall have a maximum length
of 60 meters
Under PD 957, what is the 4
minimum lot frontage for row
houses?
Under BP220, what is the 3.5 Meters
minimum lot frontage for
socialized row houses?
Which of the following is not Yard
part of the RROW?
What is the minimum RROW Verify Answer
access to an Interior lot?