PROFESSIONAL CERTIFICATION PRACTICE
EXAM Newest (2025 - 2026 Update) From Real
Past Papers Questions – Set 100 Most
Common Exam Frequently Tested Questions
And Answers In Details 100% Verified Exam
Highly Recommendable For Grade A+
1. In Design-Build project delivery, what is the primary responsibility of the
Design-Builder?
A. To act solely as the construction contractor
B. To provide financing for the project
C. To be contractually responsible for both design and construction
D. To oversee only subcontractors
✔ Correct Answer: C. To be contractually responsible for both design and
construction
Explanation: The Design-Builder holds single-point responsibility for both
design and construction, which is the defining feature of the Design-Build
delivery method.
2. Which project delivery method emphasizes a single contract between
owner and builder for both design and construction services?
A. Design-Bid-Build
B. Construction Management at Risk
C. Design-Build
D. Integrated Project Delivery
✔ Correct Answer: C. Design-Build
, Explanation: Design-Build consolidates design and construction under one
contract, improving efficiency and accountability.
3. What is the primary advantage of Design-Build over Design-Bid-Build?
A. Increased litigation
B. Reduced collaboration
C. Faster project delivery
D. More design errors
✔ Correct Answer: C. Faster project delivery
Explanation: Overlapping design and construction phases accelerates
project completion.
4. In Design-Build, who typically assumes the risk for design errors?
A. Owner
B. Architect only
C. Contractor only
D. Design-Builder
✔ Correct Answer: D. Design-Builder
Explanation: The Design-Builder assumes responsibility for both design and
construction risks.
5. Which document outlines the owner’s requirements in a Design-Build
project?
A. Construction drawings
B. Owner’s Program
C. Subcontract agreement
D. Bid schedule
✔ Correct Answer: B. Owner’s Program
Explanation: The Owner’s Program defines project goals, scope, and
performance requirements.
6. What is a key characteristic of Design-Build procurement?
A. Sequential phases
B. Competitive bidding only
, C. Qualifications-based selection
D. No owner involvement
✔ Correct Answer: C. Qualifications-based selection
Explanation: Owners often select Design-Builders based on qualifications
and value, not just price.
7. What role does the Owner play in Design-Build?
A. No involvement after contract award
B. Full control of subcontractors
C. Active involvement in defining requirements
D. Responsible for design coordination
✔ Correct Answer: C. Active involvement in defining requirements
Explanation: The Owner defines expectations and performance criteria
early in the process.
8. Which contract type is commonly used in Design-Build?
A. Lump sum or guaranteed maximum price
B. Time and materials only
C. Cost-plus without limit
D. Verbal agreement
✔ Correct Answer: A. Lump sum or guaranteed maximum price
Explanation: These contracts provide cost certainty and risk allocation.
9. What is the main goal of Design-Build collaboration?
A. Increase disputes
B. Improve project integration
C. Delay construction
D. Reduce communication
✔ Correct Answer: B. Improve project integration
Explanation: Collaboration ensures alignment between design and
construction teams.
10.What does “single point of responsibility” mean?
A. Multiple contractors share risk