1. A construction contract administrator is primarily responsible for which of
the following duties?
A. Designing structural components of the project
B. Managing contract compliance and documentation during construction
C. Performing on-site manual labor inspections exclusively
D. Preparing architectural renderings for client approval
Answer: B ✔
Rationale: The contract administrator ensures contract compliance,
documentation control, and proper execution of contract terms, not
design or labor execution.
2. Which document has the highest authority in resolving conflicts in
construction documents?
A. Contractor’s daily report
B. Specifications
C. Drawings
D. Owner’s meeting minutes
Answer: B ✔
Rationale: In most standard contracts, specifications take precedence over
drawings when conflicts arise.
,3. A contractor submits a Request for Information (RFI). The primary purpose
is to:
A. Request payment adjustment
B. Clarify ambiguities in contract documents
C. Request project termination
D. Approve subcontractor selection
Answer: B ✔
Rationale: An RFI is used to clarify design intent or document ambiguity,
not for financial or contractual termination purposes.
4. A change order is typically used to:
A. Extend project warranty
B. Modify contract scope, time, or cost
C. Replace the contractor
D. Approve safety procedures
Answer: B ✔
Rationale: A change order formally modifies contract terms including
scope, cost, or schedule.
5. The critical path in a construction schedule represents:
A. The shortest possible route to project completion
B. Activities with float
C. The sequence of activities that determines project duration
D. Non-dependent activities
Answer: C ✔
Rationale: The critical path defines the longest sequence of dependent
activities controlling project duration.
6. A pay application submitted by a contractor is primarily used to:
A. Request design changes
B. Request periodic payment for completed work
C. Submit safety violations
D. Request subcontractor approval
Answer: B ✔
, *Rationale: Pay applications document work completed and request
payment based on progress.
7. If drawings and specifications conflict, the contract administrator should
first:
A. Ignore specifications
B. Refer to the contract document hierarchy
C. Approve contractor interpretation immediately
D. Stop the project permanently
Answer: B ✔
Rationale: The administrator must follow the document hierarchy defined
in the contract before making decisions.
8. A construction claim differs from a change order because a claim:
A. Is always pre-approved
B. Is a disputed request for compensation or time
C. Is used for scheduling only
D. Cannot involve cost
Answer: B ✔
Rationale: A claim arises when compensation or time extension is
disputed.
9. Which party typically has authority to approve a substitution request?
A. Contractor only
B. Architect/Engineer or Contract Administrator
C. Subcontractor
D. Supplier
Answer: B ✔
*Rationale: Design professionals or contract administrators evaluate and
approve substitutions based on equivalency.
10.Submittals are primarily used to:
A. Replace contract documents
B. Demonstrate compliance with design intent