Which of the following balancing control modes is used by PJM under normal
operations? - correct-answer -Tie-Line Bias
Which of the following influences does PJM consider when performing their
system load forecast? - correct-answer -Weather Conditions & Day of the Week
All of the following are limits that must be submitted to PJM for generating units
EXCEPT:
1. Eco Min
2. Eco Max
3. Emergency Max
,2|Page
4. Dynamic Instability - correct-answer -Dynamic Instability
If PJM experienced an event that caused the loss of a 1,000 MW generator, which
of the following would most likely provide the quickest impact to improve the
undegenerating Area Control Area (ACE)?
1. Remedial Action Reserve
2. Synch Reserve
3. Non-Synch Reserve
4. Secondary Reserve - correct-answer -Synch Reserve
Your system has experienced an event that caused the frequency to drop below
60.00 Hz, what would be the most likely event that occurred? - correct-answer -A
generator on your system tripped offline
,3|Page
How does the PJM dispatcher inform the Members of the PJM regulation
Requirements? - correct-answer -All-Call
In order for your generator to quality to supply regulation in the PJM Regulation
market, it must be able to respond and attain its desired output within how many
minutes? - correct-answer -5 minutes
Based on a generator capability curve, in order to maximize the MVAR output of
the generator, it may be necessary to: - correct-answer -decrease the MW output
of the unit
PJM maintains a regulation quality standard which states that a generator may be
certified to provide regulation only after it achieves three consecutive regulation
test scores of at least - correct-answer -75%
, 4|Page
Which of the following would NOT be a cause for a sudden deviation in the
balancing area ACE?
1. incorrect interchange number
2. loss of a tie-line RTU
3. loss of internal load
4. loss of adjacent control area generation - correct-answer -loss of adjacent
control area generation
The primary purpose for the balancing area to have Regulation is to correct for: -
correct-answer -small deviations in load
It is necessary for Generation Owner dispatchers to notify PJM of unplanned unit
outages: - correct-answer -as soon as practicable