What is not included in the technical specification? -
correct answer ✅General Conditions
Bid documents include? -
correct answer ✅•contract
•specifications
•contract drawings
Codes, standards, Authority Having Jurisdiction (AHJ), clean-up,
safety requirements, barricades, fencing, insurance and bond
requirements, ect. -
correct answer ✅General Conditions
Addendums, time schedules, working days allowed, delay
agreements, payment schedules -
correct answer ✅Supplementary Conditions
Specifications typically use what format? -
correct answer ✅Construction Specifications Institute (CSI)
,NICET LEVEL III WATER BASED
LAYOUT EXAM QUESTIONS AND
ANSWERS
Construction manager concept is when the owner contracts with
the construction manager who oversees ____________ working on
the project -
correct answer ✅Contractors
Sometimes referred to as a turn-key type agreement or contract? -
correct answer ✅Design-Build Concept
Multiple Prime Contractor Method has the intent is eliminate the
middleman __________ __________. -
correct answer ✅general contractor
Multiple prime contractor method involve more than one prime
contractor which consist of? -
correct answer ✅•architectural/structural contractor
•mechanical contractor
•electrical contractor
Who commonly uses the multiple prime contractor method? -
correct answer ✅•federal government
•general services administration (GSA)
,NICET LEVEL III WATER BASED
LAYOUT EXAM QUESTIONS AND
ANSWERS
•large companies
Traditional method contract uses the typical chain of command
which is? -
correct answer ✅Owner, architect, general contractor,
subcontractor
General contractors can be chosen in a number of different ways
which is? -
correct answer ✅•open bid method
•bid-by invitation procedure
•direct contractor selection
Contract conditions is divided into two categories which is? -
correct answer ✅General category and supplementary conditions
Changes to the contract or other modifications. -
correct answer ✅Addendum
, NICET LEVEL III WATER BASED
LAYOUT EXAM QUESTIONS AND
ANSWERS
Types of payment schedules are? -
correct answer ✅•up-front payments
•progress payments
•lump sum
What comprises the project manual? -
correct answer ✅Bidding requirements, sample forms, conditions
of the contract and specifications, including general conditions and
supplementary conditions
Contract documents include: -
correct answer ✅•contract itself
•contract conditions
•specifications
•drawings
Drawings have different stages which are? -
correct answer ✅Preliminary, bid, approval, construction, as-built
LAYOUT EXAM QUESTIONS AND
ANSWERS
What is not included in the technical specification? -
correct answer ✅General Conditions
Bid documents include? -
correct answer ✅•contract
•specifications
•contract drawings
Codes, standards, Authority Having Jurisdiction (AHJ), clean-up,
safety requirements, barricades, fencing, insurance and bond
requirements, ect. -
correct answer ✅General Conditions
Addendums, time schedules, working days allowed, delay
agreements, payment schedules -
correct answer ✅Supplementary Conditions
Specifications typically use what format? -
correct answer ✅Construction Specifications Institute (CSI)
,NICET LEVEL III WATER BASED
LAYOUT EXAM QUESTIONS AND
ANSWERS
Construction manager concept is when the owner contracts with
the construction manager who oversees ____________ working on
the project -
correct answer ✅Contractors
Sometimes referred to as a turn-key type agreement or contract? -
correct answer ✅Design-Build Concept
Multiple Prime Contractor Method has the intent is eliminate the
middleman __________ __________. -
correct answer ✅general contractor
Multiple prime contractor method involve more than one prime
contractor which consist of? -
correct answer ✅•architectural/structural contractor
•mechanical contractor
•electrical contractor
Who commonly uses the multiple prime contractor method? -
correct answer ✅•federal government
•general services administration (GSA)
,NICET LEVEL III WATER BASED
LAYOUT EXAM QUESTIONS AND
ANSWERS
•large companies
Traditional method contract uses the typical chain of command
which is? -
correct answer ✅Owner, architect, general contractor,
subcontractor
General contractors can be chosen in a number of different ways
which is? -
correct answer ✅•open bid method
•bid-by invitation procedure
•direct contractor selection
Contract conditions is divided into two categories which is? -
correct answer ✅General category and supplementary conditions
Changes to the contract or other modifications. -
correct answer ✅Addendum
, NICET LEVEL III WATER BASED
LAYOUT EXAM QUESTIONS AND
ANSWERS
Types of payment schedules are? -
correct answer ✅•up-front payments
•progress payments
•lump sum
What comprises the project manual? -
correct answer ✅Bidding requirements, sample forms, conditions
of the contract and specifications, including general conditions and
supplementary conditions
Contract documents include: -
correct answer ✅•contract itself
•contract conditions
•specifications
•drawings
Drawings have different stages which are? -
correct answer ✅Preliminary, bid, approval, construction, as-built