Which of the following situations would warrant the Reliability Coordinator to initiate a NERC RC
conference call?
A. Energy Emergency Alert 3
B. Code of Conduct violation
C. Interchange transaction error
D. 115 kV capacitor tripping - ANSWERS-Energy Emergency Alert 3
The next day security analysis performed by the RC shall ensure that _________.
A. the bulk power system can be operated in anticipated normal and contingency conditions
B. all unavailable generation and transmission made available
C. all interchange is scheduled
D. the load forecast is within 5% of actual - ANSWERS-the bulk power system can be operated in
anticipated normal and contingency conditions
If the estimated charging incurred from switching a 500 kV line in service is 1.7 MVAR per mile,
what would be incurred if a 100 mile long 500 kV line were switched in service?
A. 85 MVAR
B. 170 MVAR
C. 850 MVAR
D. It cannot be calculated with the information provided - ANSWERS-170 MVAR
, All of the following are reasons to notify other systems through predetermined communication
paths EXCEPT:
A. Insufficient resources
B. Lack of single contingency coverage
C. Sabotage incident
D. Loss of 10 MW of load - ANSWERS-Loss of 10 MW of load ?
What would be the most likely event if the frequency in your Balancing Authority Area declines
and the interchange out of your area increased?
A. An internal generator tripped
B. An external generator tripped
C. Internal load was lost
D. External load was lost - ANSWERS-An external generator tripped
What is the major role of the EMS State Estimator?
A. Identifies the contingencies that exist on the power system
B. Estimates the system load that is anticipated at the peak of the day
C. Calculates SE values based on telemetered data and system model
D. Establishes the values that the system operator must operate within - ANSWERS-Calculates
SE values based on telemetered data and system model
Which of the following is NOT an indication of pending voltage collapse?
Solutions11
Which of the following situations would warrant the Reliability Coordinator to initiate a NERC RC
conference call?
A. Energy Emergency Alert 3
B. Code of Conduct violation
C. Interchange transaction error
D. 115 kV capacitor tripping - ANSWERS-Energy Emergency Alert 3
The next day security analysis performed by the RC shall ensure that _________.
A. the bulk power system can be operated in anticipated normal and contingency conditions
B. all unavailable generation and transmission made available
C. all interchange is scheduled
D. the load forecast is within 5% of actual - ANSWERS-the bulk power system can be operated in
anticipated normal and contingency conditions
If the estimated charging incurred from switching a 500 kV line in service is 1.7 MVAR per mile,
what would be incurred if a 100 mile long 500 kV line were switched in service?
A. 85 MVAR
B. 170 MVAR
C. 850 MVAR
D. It cannot be calculated with the information provided - ANSWERS-170 MVAR
, All of the following are reasons to notify other systems through predetermined communication
paths EXCEPT:
A. Insufficient resources
B. Lack of single contingency coverage
C. Sabotage incident
D. Loss of 10 MW of load - ANSWERS-Loss of 10 MW of load ?
What would be the most likely event if the frequency in your Balancing Authority Area declines
and the interchange out of your area increased?
A. An internal generator tripped
B. An external generator tripped
C. Internal load was lost
D. External load was lost - ANSWERS-An external generator tripped
What is the major role of the EMS State Estimator?
A. Identifies the contingencies that exist on the power system
B. Estimates the system load that is anticipated at the peak of the day
C. Calculates SE values based on telemetered data and system model
D. Establishes the values that the system operator must operate within - ANSWERS-Calculates
SE values based on telemetered data and system model
Which of the following is NOT an indication of pending voltage collapse?