Market research is conducted during which phase of acquisition?
- ANSWER-All phases of the acquisition
Feedback: See FAR 10.001(a)(2)(vi)
What would be the preferred way to acquire an item in
Government contracting? - ANSWER-Purchase the requirement
as a commercial item.
Feedback: See FAR 10.002(d)
What is the objective of a source selection? - ANSWER-To select
the proposal that represents the best value
Feedback: See FAR 15.302
When holding discussions with offerors in a source selection, all
the following must be discussed EXCEPT: - ANSWER-Price
, Page |2
You're administering a large dollar non-commercial weapons
contract. The contracting officer asks to see the Contract Data
Requirements List (CDRL) in Exhibit B. Which uniform contract
format (UCF) section in your contract would you refer to? -
ANSWER-Section J
Feedback: See FAR 14.201-4 & 15.204-4
Which of the following statements is accurate regarding the
Government's policy on contract modifications? - ANSWER-Only
contracting officers acting within the scope of their authority are
authorized to execute contract modifications on behalf of the
Government
Feedback: See FAR 43.102
Upon notice that a protest has been filed with the Government
Accountability Office (GAO), who must immediately begin
compiling the information necessary for a report to the GAO? -
ANSWER-The contracting officer
Feedback: See FAR 33.104(3)(i)
, Page |3
Which of the following reflects market research policy? Market
research: - ANSWER-Aids in determining if sources capable of
satisfying the agency's requirements exist
Feedback: See FAR 10.001
During discussions, the contracting officer: - ANSWER-Should
discuss aspects of an offeror's proposal if alterations or
explanations would enhance the proposal's potential for award
What FAR part covers protests? - ANSWER-FAR part 33
Feedback: See FAR 33.000
Acme Company did not make the competitive range in a source
selection. When the contracting officer asks for final proposal
revisions, the contracting officer: - ANSWER-Will not contact
Acme Company since it is no longer in the competition
The DoD Procurement Instrument Identifier (PIID) is 13 positions
long. Position 9 identifies the type of instrument. If position 9 is a
"D", which of the following types of instruments is representative?
, Page |4
- ANSWER-Indefinite-delivery contracts to include IDIQs and
requirements contracts
Feedback: See FAR 4.1603(a)(3)
Which of the following is an exception to obtaining certified cost or
pricing data? - ANSWER-Adequate price competition
Select the order for the proposal evaluation process. - ANSWER-
Evaluate initial proposals, determine the competitive range,
negotiate, request final proposal revisions, award the contract
Feedback: See FAR subpart 15.3
In a Determination and Findings, the findings are: - ANSWER-
Support for the determination
Feedback: See FAR 1.701
Which FAR part sets forth the basic policies and general
information about the Federal Acquisition Regulation System? -
ANSWER-FAR part 1
Feedback: See FAR 1.000