Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Document preview thumbnail
Voorbeeld 2 van de 10 pagina's
Tentamen (uitwerkingen)

CM 1011- Kimberly Williams Exam 1 UPDATED ACTUAL Questions and CORRECT Answers

Document preview thumbnail
Voorbeeld 2 van de 10 pagina's

CM 1011- Kimberly Williams Exam 1 UPDATED ACTUAL Questions and CORRECT Answers

Voorbeeld van de inhoud

CM 1011- Kimberly Williams Exam 1 UPDATED ACTUAL
Questions and CORRECT Answers

Sub-contractors, sub-sub-contractors and sub-sub-sub- 1st level of the secondary players
contractors under the prime contractor are
entities that directly a±ect the project and are classified
as:


What is the name of the document issued by the owner Request for Qualifications
prior to Request for proposals (RFP) to solicit
contractor or design-builder qualifications?


What are general conditions? Indirect costs incurred to construct a project and run a job


Technical specifications make up the bulk of the Project Actual construction of the project?
Manual. Whereas, the bidding documents,
general conditions, and supplemental conditions deal
primarily with administrative aspects of the
project, the specifications deal with the:


A contracting methodology in which the owner bypasses Multiple prime
the use of a general contractor and enters
into multiple separate contracts with trade or specialty
contractors for the various sections of the
work is:


Obtaining the building permit is an example of project Administrative activities
activity. This activity belongs to which type of
the three activities that are included in the typical
schedule?


Which of the following is a direct cost: D. Subcontracts
A. Job trailer
B. Bonds
C. Insurance
D. Subcontracts


Which of the following sums up the role of a field D. All of the above
engineer?
A. Works directly for the superintendent
B. Responsible for project layout and dimensional
accuracy
C. Responsible for communication with subcontractors
D. All of the above

, Which of the following contracts is the most common on D. Unit-priced
highway construction projects?
A. Lump Sum
B. Cost-plus-fee
C. Guaranteed maximum price
D. Unit-priced


A Qualification-Based Selection (QBS) is mostly used by: Private owners


All of the following are stages of building a schedule A. The plotting stage
except?


A. The plotting stage
B. The planning stage
C. The scheduling stage
D. The sequencing stage


Costs not directly attributable to any one work item, but D. All of the above
necessary if the project is to be built are
sometimes called indirect costs or project overhead
costs. These costs may include:
A. The superintendent costs
B. Onsite construction o±ice
C. Bonds and insurances
D. All of the above


What might be the consequences of an inaccurate D. B and C
estimate?
A. There are no consequences because the estimate is
not legally binding
B. If you overestimate you may not win the job
C. If you underestimate you will lose money on job
D. B and C


What of the following best defines the lead time? C. The amount of time it takes for a product or equipment to be delivered to the
A. A daily amount of money paid by the contractor to the job site
owner for each day that the project fails to meet the
adjusted
completion date
B. A tool used by estimators to organize the work of a
contract in a hierarchical fashion.
C. The amount of time it takes for a product or equipment
to be delivered to the job site.
D. A term commonly used in construction estimating to
describe the taxes, overhead, and profit added to the
estimate a²er all
other costs have been calculated.

Documentinformatie

Geüpload op
25 februari 2026
Aantal pagina's
10
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden
$12.49

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
MGRADES
3.8
(249)
Verkocht
1494
Volgers
106
Items
106749
Laatst verkocht
1 dag geleden


Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen