It is important that the ________ read and understand project specifications. -
CORRECT ANSWER Finisher Foreman
QUESTION : When concrete for a slab placement will be discharged from the
truck chute, truck arrivals should usually be spaced at about: - CORRECT
ANSWER 15 Min.
QUESTION : The question, "What finisher(s) can request the addition of water
to the concrete truck on site?" should be answered at the __________ -
CORRECT ANSWER Preconstruction meeting
QUESTION : Portland cement will set and harden under water, true or false? -
CORRECT ANSWER True
QUESTION : If a concrete slab on ground won't be exposed to sulfates, the
cement used is most likely to be: - CORRECT ANSWER Type 1
QUESTION : Most concrete used in slabs on ground has coarse aggregate with a
maximum size of: - CORRECT ANSWER 3/4" - 1-1/2."
UPDATED exam 2026
, 2|Page
QUESTION : Increasing the amount of sand in concrete usually decreases the
amount of water needed to make the concrete workable. True or False -
CORRECT ANSWER False
QUESTION : Granular subbases for slabs on ground can be compacted with
sheepsfoot rollers. True or False? - CORRECT ANSWER False
QUESTION : Before concreting, workers should check the elevation of the
subbase by: - CORRECT ANSWER Measuring down from a straightedge
spanning between the side forms.
QUESTION : when specifications don't require a concrete slab to be in direct
contact with the vapor retarder, the preferred method for reducing potential
problems caused by slab curing is: - CORRECT ANSWER Placing a 3"
thick layer of compactible manufactured sand (containing rock dust) on the
vapor retarder before concrete placement
QUESTION : The primary function of welded wire reinforcement in SOG that are
considered unreinforced is: - CORRECT ANSWER Keeping any slab
cracks tightly closed.
QUESTION : Instructions on drawings for SOG may require that: - CORRECT
ANSWER Reinforcing steel be discontinued (cut) so it doesn't pass through
the joint & every other bar or wire be discontinued (cut) so only half the steel
passes through the joint
QUESTION : Keyed construction joints are not recommended for slabs less than
____ thick. - CORRECT ANSWER 6"