IME 456 EXAM I QUIZZES QUESTIONS AND ANSWERS
Project Objective - CORRECT ANSWER✅✅The _______________ usually states the time by which a
project scope must be completed in terms of the specific date agreed upon by the sponsor.



False - CORRECT ANSWER✅✅T/F: People are the only resource used in a project.



True - CORRECT ANSWER✅✅T/F: When establishing the project objectives, the objective must be
agreed upon by the project sponsor.



True - CORRECT ANSWER✅✅T/F: The sponsor provides funds to accomplish the project.



True - CORRECT ANSWER✅✅T/F: The project scope document should include a list of deliverables and
associated acceptance criteria.



True - CORRECT ANSWER✅✅T/F: The amount the sponsor has agreed to pay for acceptable project
deliverables is the project budget.



Closing Phase - CORRECT ANSWER✅✅Projects documents are typically organized and archived during
the ____________



False - CORRECT ANSWER✅✅T/F: The level of effort is typically the same for all four phases of the
generic project life cycle.



True - CORRECT ANSWER✅✅T/F: Resources can include people, organizations, equipment, materials,
and facilities.



True - CORRECT ANSWER✅✅T/F: The project objective requires completing the project work scope and
producing all the deliverables by a certain time and within budget.



True - CORRECT ANSWER✅✅T/F: The Project Management Institute is a worldwide not-for-profit
organization of practitioners that certifies project management professionals.

, True - CORRECT ANSWER✅✅T/F: A project is a temporary endeavor undertaken to create a unique
product, service, or result.



Preforming Phase - CORRECT ANSWER✅✅The project plan is executed in the ___________



Risk Management - CORRECT ANSWER✅✅A ______________ plan must be developed that identifies
and assesses potential risks, determines the likelihood of occurrence and potential impacts of risks, and
delineates responses for dealing with risks.



True - CORRECT ANSWER✅✅T/F: A person or organization responsible for each work item should be
identified to assign responsibility to while planning the project.



Preforming Phase - CORRECT ANSWER✅✅Typically the vast majority of the actual "work" or "effort" to
achieve the project objective is spent during the ________________.



True - CORRECT ANSWER✅✅T/F: The project scope is all the work that must be done in order to
produce all the project deliverables, satisfy the customer, and accomplish the project objective.



True - CORRECT ANSWER✅✅T/F: The sponsor provides funds to accomplish the project.



A) Emptying the recycling bins everyday - CORRECT ANSWER✅✅Which of the following is not an
example of a project?



A) Emptying the recycling bins everyday

B) Raising money for a disaster relief trip

C) Creating a website for a company

D) Starting-up a restaurant



Initiating Phase - CORRECT ANSWER✅✅Projects are identified and selected to be "funded" or actually
"completed" in the ____________.

Written for

Institution
IME 456
Course
IME 456

Document information

Uploaded on
February 3, 2026
Number of pages
8
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

  • ime 456

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
STANGRADES Stanford University
View profile
Follow You need to be logged in order to follow users or courses
Sold
55
Member since
1 year
Number of followers
1
Documents
10294
Last sold
1 day ago
STAN-GRADES

EXCELLENCY IN ACADEMIC MATERIALS

3.4

11 reviews

5
4
4
1
3
3
2
1
1
2

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions