Question 1
The ______ consists of daily checks of the work to assure continuing compliance with contract requirements
Correct Answer
Follow-up phase
Question 2
Design-Build contracts require:
Correct Answer
The QC Manager to be in place and take an active role in the review and coordination of the design
Question 3
Which of the following is included in all three phases of the Three Phases of Control
Correct Answer
Safety
Page 1 of 11
, Question 4
The purpose of Construction Quality Management is to
Correct Answer
Achieve the quality established by properly developed requirements through the combined responsibility, but
separate, efforts of contractor and Government personnel
Question 5
Testing is extremely important in Construction Quality Management and is performed by
Correct Answer
Both the contractor and the Government
Question 6
The primary purpose of the Three-Phase Control System is to:
Correct Answer
Require the contractor to plan, schedule, and perform quality management actions to assure work meets all specified
quality standards
Question 7
Quality Assurance Personnel have the responsibility to:
Correct Answer
require the contractor to maintain the quality specified in the plans and specifications
Page 2 of 11