Public Works - California Contractors (Law
and Business) Questions and Correct
Answers/ Latest Update / Already Graded
Which of the following costs are significant when bidding on public
works projects?
A. Bonds
B. Wages
C. Insurance
D. Overhead cost
Ans: B. Wages
Of the following, who may NOT file a stop notice on a public works?
A. The prime contractor
B. Subcontractor
C. Material supplier
D. Surveyor
Ans: A. The prime contractor
All rights reserved © 2025/ 2026 |
, Page |2
What is one of the documents needed for a public works contract?
A. Contractor's license
B. A notarized list of materials to be used
C. Employee salaries and job description
D. Driver's license
Ans: A. Contractor's license
Which of the following may request a change order on a public works
project?
A. Contractor
B. City
C. Subcontractor
D. CSLB
Ans: B. City
What is the MAJOR difference between public and private works
projects?