100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.6 TrustPilot
logo-home
Exam (elaborations)

CM 443 Conceptual Est.-QUESTIONS WITH ANSWERS| 2026 | 100% Correct

Rating
-
Sold
-
Pages
49
Grade
A+
Uploaded on
19-01-2026
Written in
2025/2026

CM 443 Conceptual Est.-QUESTIONS WITH ANSWERS| 2026 | 100% Correct

Institution
CM 443
Course
CM 443











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
CM 443
Course
CM 443

Document information

Uploaded on
January 19, 2026
Number of pages
49
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

CM 443 Conceptual Est.-QUESTIONS WITH
ANSWERS| 2026 | 100% Correct
True

A contractor's estimating department is responsible for identifying the goals and objectives of the

department.

Pre-Solicitation Notice

Agencies of the U.S. government use a standard form called the "____" to provide bid

information.

advertisements in newspapers

All of the following are considered primary sources of information for private bids EXCEPT:

prequalified

A method of addressing the problem of bids from contractors of questionable capability is to call

for bids from ____ contractors only.

query list

A method of handling the problem of review questions is to compile a list of all the questions

that arise, the ____, then later send a single e-mail to the prime consultant to deal with all the

items that have accumulated.

False

An effective way to plan estimating operations is to use a simple line chart form of time

schedule.

,True

Construction groups in major cities have formed associations or plan service centers where both

public and private bodies may deposit plans and specifications of projects calling for bids.

False

General clauses that have a significant impact on the cost of the work are often found in the

"back end" of specifications in the review process.

True

If an estimator does not know exactly what the computer is accomplishing in the preparation of

an estimate, the estimator will not be in control of the process.

False

In a closed bid system, the number of companies invited to bid is typically limited to no more

than ten contractors who are known to the owner or designers and who meet the qualification

criteria set by the owner.

False

In closed bidding, there is little restriction on who can submit a bid on the work.

True

Managing the estimating process includes keeping bid records, scheduling the estimator's time,

and carefully reviewing bid documents when they are obtained.

False

Many government agencies are reluctant to publish bid notices on the Internet.

,a day or two

Most companies hold an estimate review usually ___________ before the bid is due to be

submitted.

True

On most projects general contractors request two complete sets of bid documents for estimating a

project.

the amount of fee to include in the bid price

Perhaps the most important item considered at the estimate review is ____.

closed bid

Private owners often directly invite contractors to bid on their construction projects in a system

known as a(n) ____ system.

addenda

Significant details provided in response to questions about a bid will be incorporated into written

directives that are distributed to all bidders in publications known as ____.

web pages of government agencies

Which of the following is a primary source of information regarding bid calls for public works?

chief estimator

While an experienced estimator will certainly know what to look for and assess when

investigating the site, the presence of the ____ or a project superintendent on the visit will

always be valuable if only to offer alternative viewpoints in the evaluation of the data.

, quantity takeoff

A ____ is a process of measuring the work of a project in the form of a list of quantified work

items measured in accordance with a uniform set of rules.

False

A materials takeoff generally provides sufficient information for pricing.

True

An estimate begins with a quantity takeoff.

assembly

A(n) ____ is a component of the work that can be considered separately from the other parts of

the work.

True

A perimeter length is calculated from the figured dimensions that are provided on the plan of the

structure.

True

A single centerline value can be used many times over in takeoff calculations.

<>

Deductions listed with the dimensions are written in red or enclosed in ____ and noted as

deductions.

length, width, and depth

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
QUINTER New York College Of Dentistry
View profile
Follow You need to be logged in order to follow users or courses
Sold
347
Member since
2 year
Number of followers
104
Documents
38567
Last sold
2 days ago

3.5

58 reviews

5
26
4
8
3
7
2
1
1
16

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions