What determines when a Feature is ready to move to the next column in the Program Kanban?
Policies
Work in process (WIP) limits
Definition of done
Definition of ready - CORRECT ANSWERS Policies
Which two sources are most likely to help when creating a compelling product Vision? (Choose two.)
Agile Teams
Customer feedback
Competitor analysis
Stakeholder analysis
Team Backlogs - CORRECT ANSWERS Agile Teams
Customer feedback
Which aspect of whole-product thinking captures a Customer's price sensitivity?
Augmented product
Expected product
Potential product
Generic product - CORRECT ANSWERS Augmented product
,To foster alignment during the PI execution, the Product Manager may often be asked to facilitate which
event in the closed loop system?
PO sync
Scrum of Scrums
System Demo
Inspect & Adapt - CORRECT ANSWERS PO sync
What are the key elements of the Solution Intent?
Specifications, designs, and tests
Strategic Themes and nonfunctional requirements
Epics, Features, and Stories
Customer segments and product Vision - CORRECT ANSWERS Specifications, designs, and
tests
Which horizon describes the desired state as stable solutions that deliver high value with minimal new
investment?
Horizon 1
Horizon 0
Horizon 2
Horizon 3 - CORRECT ANSWERS Horizon 1
What are two outputs of a PI Planning event? (Choose two.)
Top 10 Features
PI retrospective action items
Committed PI Objectives
Program Board with Dependencies
, 10-15% allocation to the Architectural Runway - CORRECT ANSWERS Committed PI
Objectives
Program Board with Dependencies
What does the Solution Context describe?
The behavior of the Solution
The type of Solution the Customer will use
The environment in which the Solution operates
The Customer segment for the Solution - CORRECT ANSWERS The environment in which the
Solution operates
Who are the three main stakeholders involved in calculating a Feature's weighted shortest job first
values? (Choose three.)
Release Train Engineer
Product Manager
System Architects
Scrum Master
System Team
Business Owners - CORRECT ANSWERS Release Train Engineer
Which ceremony tracks the ART's progress towards meeting the Program Increment objectives?
ART sync
Participatory budgeting
Portfolio minimum viable product reviews
Weighted shortest job first prioritization - CORRECT ANSWERS ART sync
Under what circumstance would a team create a Story map?
ANSWERS 100% RATED CORRECT
WITH 100% SURE PASS|GRADED A+
What determines when a Feature is ready to move to the next column in the Program Kanban?
Policies
Work in process (WIP) limits
Definition of done
Definition of ready - CORRECT ANSWERS Policies
Which two sources are most likely to help when creating a compelling product Vision? (Choose two.)
Agile Teams
Customer feedback
Competitor analysis
Stakeholder analysis
Team Backlogs - CORRECT ANSWERS Agile Teams
Customer feedback
Which aspect of whole-product thinking captures a Customer's price sensitivity?
Augmented product
Expected product
Potential product
Generic product - CORRECT ANSWERS Augmented product
,To foster alignment during the PI execution, the Product Manager may often be asked to facilitate which
event in the closed loop system?
PO sync
Scrum of Scrums
System Demo
Inspect & Adapt - CORRECT ANSWERS PO sync
What are the key elements of the Solution Intent?
Specifications, designs, and tests
Strategic Themes and nonfunctional requirements
Epics, Features, and Stories
Customer segments and product Vision - CORRECT ANSWERS Specifications, designs, and
tests
Which horizon describes the desired state as stable solutions that deliver high value with minimal new
investment?
Horizon 1
Horizon 0
Horizon 2
Horizon 3 - CORRECT ANSWERS Horizon 1
What are two outputs of a PI Planning event? (Choose two.)
Top 10 Features
PI retrospective action items
Committed PI Objectives
Program Board with Dependencies
, 10-15% allocation to the Architectural Runway - CORRECT ANSWERS Committed PI
Objectives
Program Board with Dependencies
What does the Solution Context describe?
The behavior of the Solution
The type of Solution the Customer will use
The environment in which the Solution operates
The Customer segment for the Solution - CORRECT ANSWERS The environment in which the
Solution operates
Who are the three main stakeholders involved in calculating a Feature's weighted shortest job first
values? (Choose three.)
Release Train Engineer
Product Manager
System Architects
Scrum Master
System Team
Business Owners - CORRECT ANSWERS Release Train Engineer
Which ceremony tracks the ART's progress towards meeting the Program Increment objectives?
ART sync
Participatory budgeting
Portfolio minimum viable product reviews
Weighted shortest job first prioritization - CORRECT ANSWERS ART sync
Under what circumstance would a team create a Story map?