Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Document preview thumbnail
Voorbeeld 4 van de 39 pagina's
Tentamen (uitwerkingen)

ARE CE Tests Questions with Correct Answers | Updated (100% Correct Answers)

Document preview thumbnail
Voorbeeld 4 van de 39 pagina's

ARE CE Tests Questions with Correct Answers | Updated (100% Correct Answers)

Voorbeeld van de inhoud

1


ARE CE Tests Questions with Correct
Answers | Updated (100% Correct Answers)
Parts of a weld Answer: Leg

Throat

Face

If hazardous waste discovered during construction who pays? IE
underground storage tank Answer: Contractor pays and Owner
reimburses

-A201 states owner is responsible for remediation of hazardous
materials at project site

who has discretion to decided whether or not construction meets
design intent? Answer: architect

Costs to repair or correct work due to a design defect are payable
by Answer: the architect's professional liability insurance (errors and
omissions)

things that are included in a Life cycle cost analysis LCCA? Answer:
initial costs

maintenance costs



© 2025 All rights reserved

,2
operational costs

financing costs

are replacement costs considered in LCCA? Answer: No

just cost over lifetime of individual system

possible consequence of a dry plumbing trap? Answer: leakage of
sewer gas

make sure to distinguisher between "cause" and "consequence"
Answer: *

what consultant to deal with coaxial cable performance? Answer:
low voltage consultant

-deals with communications, security, audio, and video systems

(division 27)

who deals with high voltage systems that have a direct effect on life
safety? Answer: electrical engineer

Where to note discrepancies seen during site visit? Answer: note
the observation in a field report

Is the architect at fault for missing an incorrect dimension on shop
drawings? Answer: No


© 2025 All rights reserved

,3
Architect reviews shop drawings for design intent, and it is the
contractor's responsibility to ensure the proper dimensions

-contractor checks for proper length

Is the structural engineer at fault for missing incorrect dimensions
on shop drawings? Answer: No, same as architect

what must each bidder contractually represent? Answer: - has read
and understands provisions for liquidated damages

- must visit site

- bid is based upon the materials, equipment, and systems required
by the bidding documents without exception

three statements about privately bid projects? Answer: -owner may
open bids privately, often with arch's assist

-architect should reveal results only w/ owner approval/direction

4 points about stipulated sum contracts? Answer: -owner knows
cost at time of contract execution

-unit prices are permitted

-owner compensates contractor fixed price for work, according to
contract docs



© 2025 All rights reserved

, 4
-actual construction costs and construction bid dif are profit/loss by
the contractor

In order to properly track the progress of construction, each field
report should be... Answer: sequentially numbered

two things that should be on field report? Answer: observation date

weather conditions

-NOT schedule

contractor is compensated for direct labor, costs of subcontracts,
and material costs, as well as overhead and profit at a fixed price or
percentage - which method? Answer: cost-plus-fee

Can the architect approve minor changes without owner's consent?
Answer: Yes per AIA A201 Section 7.4

-cant add additional cost

When Party A has unfairly benefited at the expense of Party B?
Answer: Unjust Enrichment

-Under this doctrine Party B can claim restitution

Unforeseeable circumstances that prevent someone from fulfilling a
contract? Answer: force majeure



© 2025 All rights reserved

Documentinformatie

Geüpload op
16 januari 2026
Aantal pagina's
39
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden
$14.99

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
Passit
3.5
(22)
Verkocht
124
Volgers
6
Items
14454
Laatst verkocht
2 weken geleden


Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen