BADM 318 Exam Questions and
Answers 100% PASS
Which of these is NOT one of the four core values of Agile set forth in the Agile
Manifesto, published in 2001?
a. Value customer collaboration more than negotiation.
b. Value following a plan over response to change.
c. Value individuals more than processes.
d. Value working software more than documentation - CORRECT ANSWER-b.
Value following a plan over response to change.
The term _________ is a broad label that describes the people and groups who
can impact a project or might be impacted by either the work or the results of the
project.
a. business owners
b. executive management
c. stakeholders
,d. customers - CORRECT ANSWER-c. stakeholders
Which of these is NOT one of the five project management process groups
defined by the Project Management Institute in A Guide to the Project
Management Body of Knowledge® (PMBOK Guide 6e)?
a. Executing
b. Managing
c. Initiating
d. Monitoring and Controlling - CORRECT ANSWER-b. Managing
Which of the managerial roles below would NOT be found in a traditional plan-
driven project?
a. Project manager
b. Facilitator
c. Functional manager
d. Scrum master - CORRECT ANSWER-d. Scrum master
Contractor companies might determine which client projects to pursue by
performing a quick _______.
a. financial analysis
b. SWOT analysis
c. scoring model
© 2026 Copyright. All Rights Reserved. This document is
protected by copyright law
,d. business case - CORRECT ANSWER-b. SWOT analysis
An organization's ______ is/are a one-sentence statement describing the clear and
inspirational long-term, desired change or direction resulting from an organization
or program's work.
a. mission
b. strategic analysis
c. vision
d. beliefs - CORRECT ANSWER-c. vision
With the strategic analysis, mission, and vision in place, strategic objectives to
achieve the mission and vision are developed. Organizations that embrace the
triple bottom line in their guiding values will have objectives promoting each one
of them, and projects that are selected will contribute toward each. Which of these
is NOT part of an organization's triple bottom line?
a. Profit
b. People
c. Processes
d. Planet - CORRECT ANSWER-NOT CORRECT - d. Planet
, Incorrect. The triple bottom line objectives describe both short and long-term
results that are desired, along with measures to determine achievement. Planet is
one of the triple bottom line values. See 2-1c: Strategic Objectives
After a scoring model has been used to select projects, key decision makers will
prioritize them by determining which projects will be assigned resources and a start
date. Which of these issues would NOT be a consideration for prioritizing
projects?
a. The final weighted score for the project
b. The urgency of each project
c. The net present value of the project
d. The cost of delaying the expected benefit of the project - CORRECT
ANSWER-c. The net present value of the project
According to Tri-Health's decision matrix, there are a number of project
conditions under which no project charter would be required. Other situations
require either a mini charter or a full project charter. Under which of the
conditions below would a mini charter be appropriate?
a. No technology changes
b. Improvement will be tracked.
c. Little complexity
© 2026 Copyright. All Rights Reserved. This document is
protected by copyright law
Answers 100% PASS
Which of these is NOT one of the four core values of Agile set forth in the Agile
Manifesto, published in 2001?
a. Value customer collaboration more than negotiation.
b. Value following a plan over response to change.
c. Value individuals more than processes.
d. Value working software more than documentation - CORRECT ANSWER-b.
Value following a plan over response to change.
The term _________ is a broad label that describes the people and groups who
can impact a project or might be impacted by either the work or the results of the
project.
a. business owners
b. executive management
c. stakeholders
,d. customers - CORRECT ANSWER-c. stakeholders
Which of these is NOT one of the five project management process groups
defined by the Project Management Institute in A Guide to the Project
Management Body of Knowledge® (PMBOK Guide 6e)?
a. Executing
b. Managing
c. Initiating
d. Monitoring and Controlling - CORRECT ANSWER-b. Managing
Which of the managerial roles below would NOT be found in a traditional plan-
driven project?
a. Project manager
b. Facilitator
c. Functional manager
d. Scrum master - CORRECT ANSWER-d. Scrum master
Contractor companies might determine which client projects to pursue by
performing a quick _______.
a. financial analysis
b. SWOT analysis
c. scoring model
© 2026 Copyright. All Rights Reserved. This document is
protected by copyright law
,d. business case - CORRECT ANSWER-b. SWOT analysis
An organization's ______ is/are a one-sentence statement describing the clear and
inspirational long-term, desired change or direction resulting from an organization
or program's work.
a. mission
b. strategic analysis
c. vision
d. beliefs - CORRECT ANSWER-c. vision
With the strategic analysis, mission, and vision in place, strategic objectives to
achieve the mission and vision are developed. Organizations that embrace the
triple bottom line in their guiding values will have objectives promoting each one
of them, and projects that are selected will contribute toward each. Which of these
is NOT part of an organization's triple bottom line?
a. Profit
b. People
c. Processes
d. Planet - CORRECT ANSWER-NOT CORRECT - d. Planet
, Incorrect. The triple bottom line objectives describe both short and long-term
results that are desired, along with measures to determine achievement. Planet is
one of the triple bottom line values. See 2-1c: Strategic Objectives
After a scoring model has been used to select projects, key decision makers will
prioritize them by determining which projects will be assigned resources and a start
date. Which of these issues would NOT be a consideration for prioritizing
projects?
a. The final weighted score for the project
b. The urgency of each project
c. The net present value of the project
d. The cost of delaying the expected benefit of the project - CORRECT
ANSWER-c. The net present value of the project
According to Tri-Health's decision matrix, there are a number of project
conditions under which no project charter would be required. Other situations
require either a mini charter or a full project charter. Under which of the
conditions below would a mini charter be appropriate?
a. No technology changes
b. Improvement will be tracked.
c. Little complexity