The duties of a special inspector include all of the following EXCEPT:
1) review the approved plans and specifications for special inspection requirements
2) inspect work for compliance with the building department approved plans
3) notify, in writing, a report to be seen by the building official and engineer of record of
unresolved deviations
4) [ANSWER] issuing stop work notices
When reporting non-conforming items, all of the following items must be in the
report EXCEPT:
1) [ANSWER] Time of notification of the contractor
2) Name and title of each individual notified
3) Reference to applicable detail of approved plans, job specifications or code
4) Resolution or corrective action taken
Depending upon the jurisdiction, the special inspector is required to send their final
report to the building official and:
the design professional in responsible charge
The responsibility of ensuring that day to day work is covered by inspections falls
on:
the contractor
How often should nonconformance reports be sent to the building official?
As established by the building official
The _____________ ensures that all inspections are conducted as shown in the statement of
special inspections.
, special inspection agency
It is the responsibility of the ________ to monitor the special inspection activities.
building official
Special inspection reports should contain all of the following elements EXCEPT:
1) location and the details of reinforcement inspections
2) [ANSWER] relevant ASTMs
3) names of individuals notified on-site regarding areas of work
4) changes authorized by the design professional in responsible charge
The __________ is responsible for approving the special inspection program.
building official
The responsibilities of the special inspection agency are all of the following EXCEPT:
1) Review approved plans and specifications
2) Ensuring that all inspections are conducted per the statement of special inspections
3) Report non-conforming items
4) [ANSWER] Prepare special inspection program
Who does the special inspector notify first if there is a non-conforming item?
The contractor
How often does the special inspector submit reports to the building official?
As determined by the building official
Who establishes the special inspection program?
Building department
Where are the required special inspections for a project found?
The statement of special inspections
The statement of special inspections is written by the?