100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.6 TrustPilot
logo-home
Exam (elaborations)

CM 4101 FINAL QUESTIONS & ANSWERS

Rating
-
Sold
-
Pages
8
Grade
A+
Uploaded on
10-01-2026
Written in
2025/2026

CM 4101 FINAL QUESTIONS & ANSWERS

Institution
CM 4101
Module
CM 4101









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
CM 4101
Module
CM 4101

Document information

Uploaded on
January 10, 2026
Number of pages
8
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

CM 4101 FINAL QUESTIONS & ANSWERS

During which of the following process, questions such as what activities should be
scheduled are typically asked and answered?

a. Planning
b. Scheduling
c. Control - Answers -Planning

Using traditional bar charts, it is always easy to tell the logic relationships between
activities.

a. True
b. False - Answers -False

An event consumes

a. Resources
b. Time
c. Both Resources and Time
d. Neither resources nor time - Answers -Neither resources nor time

Which of the following is correct regarding CPM and PERT?

a. The calculations in CPM are non-deterministic and those in PERT are deterministic
b. The calculations in CPM are deterministic and those in PERT are non-deterministic
c. The calculations in both are deterministic
d. The calculations in both are non-deterministic - Answers -The calculations in CPM
are deterministic and those in PERT are non-deterministic

Assume A is a milestone of a project, which of the following statement(s) can be true?

a. A may take 3 days
b. A needs one mason and two helpers to finish
c. A costs $2,000
d. A can at least be crashed by 1 day
c. None of the above - Answers -None of the Above

An activity's scheduled early start time is at the beginning of day 10. Its duration is 5
days. Its total float is 7 days. If the activity is actually finished at the end of day 21,
which of the following statement(s) must be true?

a. The project will be delayed because of this activity
b. The status of this activity will not cause a possible delay to the entire project
c. The early start time of the successors of this activity will be delayed

, d. None of the above - Answers -The status of this activity will not cause a possible
delay to the entire project

The forward pass along in the Critical Path Method can be used to determine

a. Total Float
b. Activity early finish time
c. Activity late finish time
d. None of the above - Answers -Total Float

Arrow diagrams use link to represent activities

a. True
b. False - Answers -True

Choose all that are NOT true to a non-critical activity (Assume the total float of critical
activities is zero)

a. Total float is not equal to zero
b. Total float is smaller than free float
c. Free float is always equal to zero
d. Lag is always equal to zero
e. None of the above - Answers -Free float is always equal to zero;
Lag is always equal to zero

After resource leveling, the duration of a project may be changed?

a. True
b. False
c. Cannot be determined - Answers -False

A significant difference between "planning" and "scheduling" is:

a. Scheduling determines what is going to be done, and planning determines how to do
b. Scheduling determines how to do, and planning determines what to do
c. Scheduling determines when to do, and planning determines what to do, how to do,
and by whom
d. Scheduling determines how to do, and planning determines by whom - Answers -c.
Scheduling determines when to do, and planning determines what to do, how to do, and
by whom

What is not true about classic bar charts?

a. Bar charts use a time-scaled presentation
b. Bar charts often directly show resource consumption of each activity
c. Bar charts can show the relative of each activity

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
QUEENS Harvard University
View profile
Follow You need to be logged in order to follow users or courses
Sold
222
Member since
3 year
Number of followers
180
Documents
4152
Last sold
2 weeks ago

4.1

61 reviews

5
35
4
10
3
8
2
3
1
5

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these revision notes.

Didn't get what you expected? Choose another document

No problem! You can straightaway pick a different document that better suits what you're after.

Pay as you like, start learning straight away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and smashed it. It really can be that simple.”

Alisha Student

Frequently asked questions