1. What is the primary purpose of a tower crane load chart?
A. To determine rigging methods
B. To calculate wind speed limits
C. To show maximum allowable loads at specific radii
D. To identify operator qualifications
The load chart defines the crane’s rated capacity based on boom
length, radius, and configuration, which is critical for safe
operation.
2. When must a tower crane operator stop operations due to wind
conditions?
A. When winds exceed 10 mph
B. When winds exceed manufacturer recommendations
C. When winds cause minor load sway
D. When winds exceed the crane manufacturer’s specified limits
Manufacturers specify maximum wind speeds for safe operation,
and exceeding these limits can lead to loss of control or
structural failure.
,3. What component allows a tower crane to rotate horizontally?
A. Hoist drum
B. Mast section
C. Slewing ring
D. Counter-jib
The slewing ring is the large bearing that enables rotation of the
crane’s upper structure.
4. What is the primary hazard of side loading a tower crane?
A. Increased hoist speed
B. Cable wear
C. Structural stress and potential collapse
D. Reduced visibility
Tower cranes are designed for vertical lifts; side loading
introduces forces that can exceed structural limits.
5. Who is responsible for ensuring the load is properly rigged?
A. The signal person
B. The site supervisor
C. The crane operator
D. The project engineer
Although riggers assist, the operator has final responsibility to
ensure the load is safely rigged before lifting.
6. What should an operator do if the load begins to swing
uncontrollably?
A. Increase hoist speed
B. Stop and lower the load immediately
C. Stop movement and allow the load to stabilize
D. Rotate the crane rapidly
Allowing the load to stabilize reduces dynamic forces and
prevents further swing.
, 7. What device prevents lifting loads beyond rated capacity?
A. Wind gauge
B. Hoist brake
C. Load moment indicator (LMI)
D. Anti-collision system
The LMI monitors load weight and radius to prevent overload
conditions.
8. Before climbing or erecting a tower crane, what must be verified?
A. Operator experience
B. Concrete color
C. Foundation strength and cure time
D. Load chart version
A properly cured and engineered foundation is essential to
support the crane’s loads.
9. What is the function of counterweights?
A. Increase hoist speed
B. Improve visibility
C. Balance the load and reduce tipping forces
D. Reduce wind resistance
Counterweights offset the load on the jib, maintaining stability.
10. Which hand signal indicates “emergency stop”?
A. One arm raised
B. Arms extended horizontally
C. Both arms extended with palms down and moved rapidly
D. Finger pointing upward
Emergency stop signals must be immediately recognized and
obeyed.
11. What inspection must be performed daily before operation?
A. Structural engineering analysis