Which of the following defines runoff?
a. the wearing away of soil by wind or water
b. the soil that is washed from the land into water, usually after rainfall
c. the rain, snow melt, and irrigation water that appears in streams, rivers, drains, and sewers - CORRECT
ANSWER✅✅C
What is an SWPPP?
a. a plan that describes the measures that will be taken on a site to control stormwater pollution
b. a best management practice that controls runoff, erosion, or sediment
c. a permit that authorizes a category of stormwater discharges under the CWA within a geographical
area - CORRECT ANSWER✅✅A
Which type of BMP is implemented to maintain a clean jobsite?
a. erosion control
b. good housekeeping measures
c. sediment control - CORRECT ANSWER✅✅B
What's the purpose of a stabilized construction entrance?
a. to compact the sediment attached to the wheels of construction vehicles
b. to reduce the amount of runoff leaving the jobsite
c. to minimize the amount of soil being tracked from the jobsite - CORRECT ANSWER✅✅C
When must changes be made to the SWPPP?
a. before the NOI is posted
b. when the CGP is updated during the construction project
c. when a BMP is found to be ineffective during an inspection - CORRECT ANSWER✅✅C
Which of the following does the site supervisor have to do after an inspection?
, a. Resubmit the SWPPP.
b. Prepare an inspection report.
c. Submit a Notice of Intent. - CORRECT ANSWER✅✅B
When is the Notice of Termination filed?
a. once construction has ceased and the area is stabilized
b. before development and construction begin
c. during the construction phase - CORRECT ANSWER✅✅A
When can the builder stop conducting SWPPP inspections and maintenance on the site?
a. when the SWPPP is complete and the NOI has been filed
b. after the rainy season has ended
c. when construction is complete and all areas of the site have been permanently stabilized - CORRECT
ANSWER✅✅C
When a storm or rainfall isn't in the forecast, how does the site supervisor know when to inspect each
BMP?
a. Look at the site plan.
b. Check the maintenance schedule laid out in the SWPPP.
c. Read the CGP for inspection requirements. - CORRECT ANSWER✅✅B
How does a visit from a compliance inspector usually end?
a. with a review of the CGP
b. with an exit interview
c. with the issuance of any applicable citations - CORRECT ANSWER✅✅B
Which of the following is a good way to improve the chances of the SWPPP being effective?
a. minimizing BMP repairs and maintenance
b. increasing erosion throughout the site