100% tevredenheidsgarantie Direct beschikbaar na betaling Zowel online als in PDF Je zit nergens aan vast
logo-home
PMP EXAM QUESTIONS AND CORRECT ANSWERS WELL RATED AND UPDATED €19,39   In winkelwagen

Tentamen (uitwerkingen)

PMP EXAM QUESTIONS AND CORRECT ANSWERS WELL RATED AND UPDATED

 28 keer bekeken  1 keer verkocht
  • Vak
  • Instelling

PMP EXAM QUESTIONS AND CORRECT ANSWERS WELL RATED AND UPDATED

Voorbeeld 4 van de 72  pagina's

  • 5 februari 2024
  • 72
  • 2023/2024
  • Tentamen (uitwerkingen)
  • Vragen en antwoorden
avatar-seller
PMP EXAM QUESTIONS AND CORRECT
ANSWERS WELL RATED
AND UPDATED

The critical element in a project's communication system is the:
Progress report
Project directive
Project manager
Customer Correct Ans - Project manager

, PMP EXAM QUESTIONS AND CORRECT
ANSWERS WELL RATED
AND UPDATED


Project scope is:


All the work that must be done in order to deliver a product according to the specified
features and functions, only.


The features and functions that are to be included in a product or service. A
narrative description of work to be performed under contract.
All of the above Correct Ans - All the work that must be done in order to
deliver a product according to the specified features and functions, only.


The most important criteria in deciding to initiate a project selection method is:


Stakeholder's vision
Low cost opportunity
Environmental consideration


Capability Correct Ans - Environmental consideration Which
of the following is not a General management technique? Make-or-buy
analysis
Analysis of alternatives
Applying PMBOK concepts
Lateral thinking Correct Ans - Make-or-buy analysis


As a project manager you have successfully delivered all project deliverables within
stipulated timelines - your senior management wants you to calculate the Cost of
Quality - as a project Manager what costs would you NOT consider while making this
calculation?

, PMP EXAM QUESTIONS AND CORRECT
ANSWERS WELL RATED
AND UPDATED

A. Cost of Hiring
B. Prevention costs
C. Appraisal costs
E. External and InternalFailure costs Correct Ans - A Cost of Hiring


All of the above are correct - except option A - since Hiring Costs have nothing to do
with Cost of Quality.

, PMP EXAM QUESTIONS AND CORRECT
ANSWERS WELL RATED
AND UPDATED


What is the BEST use of the Work Authorization System?


It manages the timing and sequence of when activities need to be performed It
manages who performs the activity
It identifies the resources needed to complete activities


It is used for comparing actual work against the baselines Correct Ans -
It manages the timing and sequence of when activities need to be performed


It defines how work will be authorized and how work will be done at the right time and
in the right sequence


You are managing a project that your company won after making a bid. The clients
have negotiated long and hard and have driven a hard bargain. The project is schedule
to span over eight months and you are in your fifth month of execution. You are
extremely worried since you have about four more months of work remaining and the
project is at the "Point of total assumption" - what does this mean?


As a seller you are running behind schedule As
a seller you are ahead of schedule
The project is going to have a cost overrun which will need to be negotiated with the
client


As a sellter all subsequent costs will have to be borne by the sellter
Correct Ans - As a seller all subsequent costs will have to be borne by the
seller


Reason: "Point of assumption" is the point at which the seller has consumed all the

Voordelen van het kopen van samenvattingen bij Stuvia op een rij:

√  	Verzekerd van kwaliteit door reviews

√ Verzekerd van kwaliteit door reviews

Stuvia-klanten hebben meer dan 700.000 samenvattingen beoordeeld. Zo weet je zeker dat je de beste documenten koopt!

Snel en makkelijk kopen

Snel en makkelijk kopen

Je betaalt supersnel en eenmalig met iDeal, Bancontact of creditcard voor de samenvatting. Zonder lidmaatschap.

Focus op de essentie

Focus op de essentie

Samenvattingen worden geschreven voor en door anderen. Daarom zijn de samenvattingen altijd betrouwbaar en actueel. Zo kom je snel tot de kern!

Veelgestelde vragen

Wat krijg ik als ik dit document koop?

Je krijgt een PDF, die direct beschikbaar is na je aankoop. Het gekochte document is altijd, overal en oneindig toegankelijk via je profiel.

Tevredenheidsgarantie: hoe werkt dat?

Onze tevredenheidsgarantie zorgt ervoor dat je altijd een studiedocument vindt dat goed bij je past. Je vult een formulier in en onze klantenservice regelt de rest.

Van wie koop ik deze samenvatting?

Stuvia is een marktplaats, je koop dit document dus niet van ons, maar van verkoper jameswest. Stuvia faciliteert de betaling aan de verkoper.

Zit ik meteen vast aan een abonnement?

Nee, je koopt alleen deze samenvatting voor €19,39. Je zit daarna nergens aan vast.

Is Stuvia te vertrouwen?

4,6 sterren op Google & Trustpilot (+1000 reviews)

Afgelopen 30 dagen zijn er 85443 samenvattingen verkocht

Opgericht in 2010, al 14 jaar dé plek om samenvattingen te kopen

Start met verkopen
€19,39  1x  verkocht
  • (0)
  Kopen