Summary

Summary Critical Path Analysis

Document preview thumbnail
Preview 1 out of 2 pages

Describes what a critical path analysis is, what a manager needs to know to use the technique, features of a critical path, key points of a critical path, and the advantages and disadvantages of it.

Content preview

Theme 3 Topic 9
Critical Path Analysis
Critical Path Analysis
Critical Path Analysis – using a network diagram to show
the tasks taken to complete a project in the minimum time
possible

 Shows the sequence of activities required for the
project and the order in which they can be
completed
 Its purpose is to plan projects in a way which
enables a project to be completed in the shortest
time possible

To Use the Technique a Manager Needs to Know:

 What different tasks are involved
 The length of time each task is expected to take
 The order the tasks must be completed in – some can’t be started until another has finished

Features of a Critical Path Analysis:

Feature Explanation
Nodes and Node  The circles represent a point in time at the start or end of an activity
Numbers  Nodes are split into three
 The left half of the node contains the number of the node – provides a unique
identity for each node
Earliest Start  The right half of the node is split in two
Time (EST)  The top segment shows the EST that an activity can commence
 Depends on the completion of the previous activity
 For the starting activity, the EST is always zero
Latest Finishing  The bottom segment shows the LFT
Time (LFT)  The latest time an activity can finish without delaying the overall project
Arrows  Represent production activities, they must go left to right and begin and end
with a node
 Below the line – a number which represents the length of time it takes to
complete that activity
 Above the line – a letter or description of the activity that the line represents
The Critical Path  Critical Path – the sequence of activities in a project that must be completed
within a designated time in order to prevent any delay in overall completion of
the project
 Is shown by the symbol // over the arrow
Total Float  Total Float – the amount of time that an activity can be delayed by without
delaying the entire project
 Total Float for an Activity = LFT – Duration of Activity – EST

Key Points of a Critical Path Analysis:

 Must start and end on a single node
 No lines should cross each other
 There is no limit on the number of activities that link to a single node
 When drawing an activity, do not add the end node until you have looked to see which activity follows
 It is helpful to draw networks with large circles and short lines – able to write figures in the nodes

Advantages of Critical Path Analysis Disadvantages of Critical Path Analysis

Document information

Study Level
Subject
Uploaded on
September 28, 2020
Number of pages
2
Written in
2019/2020
Type
Summary
£3.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
emily1744
4.3
(15)
Sold
43
Followers
23
Items
168
Last sold
2 months ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these revision notes.

Didn't get what you expected? Choose another document

No problem! You can straightaway pick a different document that better suits what you're after.

Pay as you like, start learning straight away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and smashed it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions