If a contractor is infringing a copyright with the consent of the government: ✔️the copyright holder
may sue the government for monetary damages
Does a $75,000 claim resulting from a reduction of $350,000 and an increase of $275,000 require
certification? ✔️Yes, the aggregate value of the claim exceeds $100,000
Protests may be filed with ______________________. ✔️either the agency or the General
Accountability Office
Who can authorize continued performance in the face of a protest after award? ✔️The head of the
contracting activity.
A ___________________ is required only when a performance bond is required and it is determined to
be in the government's best interest to use them. ✔️payment bond
True or False? The government encourages the maximum practical commercial use of inventions made
✔️True
The government will refuse to award a contract on grounds that the prospective contractor may infringe
a patent ✔️False
True or False? The government should be indemnified against infringement of US patents. ✔️True
True or False? The government requires contractors obtain permission from copyright owners before
including privately-owned work to be delivered under contract.. ✔️True
What bond secures fulfillment of the Contractor's obligations under a patent provision? ✔️Patent
infringement bond