How many apprentices can a journeyman directly supervise? - correct answer 2

When performing any service work on a customers heating system the licensee must
notify the homeowner of? - correct answer Efficiency and code violations

Can a licensed journeyman perform a cleaning on wood/oil combination unit without
direct supervision? - correct answer No

When installing a furnace, direct wired water heater or boiler what must be done prior to
placing it in service? - correct answer Everything complies with NFPA 31 code

When installing a new oil burner the _______ must be brought into compliance with the
rules of the board before ______? - correct answer Wiring Start up

When an emergency situation arises that does not allow adequate time to get the
chimney lined/repaired before installing the new heating appliance what can be done? -
correct answer 90 day waiver

Who is responsible for ensuring repairs or the chimney is lined within the 90 days? -
correct answer Installer\Licensee

When is a heat loss required? - correct answer For new install

Prior to a boiler replacement a________ or a ________ Must be conducted before
replacement of an existing system. - correct answer Heat loss/ heat load

The low-water cut off must be located where? - correct answer 6 inches above boiler
crown sheet but in no case below

An oil supply or return line under cement subfloor or earth must be ________ And
without ________? - correct answer Sleeved Fittings (continuous)

Coated copper tubing must have _______ Installed at the tank when ________? -
correct answer OSV Underground

Whenever an outlet of an oil supply tank is located more than ______ above the burner
a _____ or _____ valve is required. - correct answer 4ft OSV or PRV

Unprotected lines that are buried or grouted must be? - correct answer removed from
service

All fuel supply tanks must be a minimum of _____ From any gas and or solid fuel
burning appliance - correct answer 5ft

, If a customer is converting to an alternative fuel and leaving the oil tank what must be
done? - correct answer Vent pipe left in place fill pipe removed and plugged supply lines
removed and plugged

Outside oil tank supports shall not be _______? - correct answer Wood

What is the required thickness of the vertical oil tank pad? - correct answer 3 inches of
solid concrete

When are shims allowed to be used on oil tank legs? - correct answer Never

Oil tanks must be disposed of in accordance with? - correct answer DEP

What are two options for supporting in inside oil tank on unfinished floors? - correct
answer 3" Cement pads\solid concrete blocks

When are vent alarms required on inside oil tanks? - correct answer Always on all tanks
11-5,000 gals

If the entrance to the boiler room is only accessible from the outside the ____________
may be placed _________? - correct answer Emergency switch. At the inside not more
than 1 foot away from the door

When can residential warm air heat exchangers be welded for a repair? - correct
answer Never

What is appendix A of the Maine fuel code? - correct answer DEP Spills

What is required to be filled out when a chimney waiver is needed? Who must sign? -
correct answer Installer and consumer signature

What is the maximum size of mini split heat pump a journeyman technician may install
in a one and two family dwelling - correct answer 36,000 BTU max

What size vent is required for waste oil tank? - correct answer 2 inch

If an oil line passes through a wall what must be installed? - correct answer Thermally
actuated valve

How far away from a water heater connection before a pex pipe connection can be
made? - correct answer 18 inches

How far off the floor should a relief valve be piped? - correct answer 6"-12"

Document information

Uploaded on
July 9, 2024
Number of pages
7
Written in
2023/2024
Type
Exam (elaborations)
Contains
Questions & answers
£10.42

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
puritywanjihia
5.0
(2)
Sold
4
Followers
1
Items
484
Last sold
3 months ago




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these revision notes.

Didn't get what you expected? Choose another document

No problem! You can straightaway pick a different document that better suits what you're after.

Pay as you like, start learning straight away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and smashed it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions