IT Unit 9 Learning Aim C Project Management (Distinction work)

Rating
-
Sold
-
Pages
34
Grade
A+
Uploaded on
24-05-2023
Written in
2022/2023

BTEC Level 3 National Diploma RQF - Unit 9 project mangement












Whoops! We can’t load your doc right now. Try again or contact support.

Document information

Uploaded on
May 24, 2023
Number of pages
34
Written in
2022/2023
Type
Essay
Professor(s)
Unknown
Grade
A+

Subjects

Content preview

lOMoARcPSD|3013804




lOMoARcPSD|3013804




Project Management
SOFTWARE DEVELOPEMENT




Project Phasing
To ensure the implementation of large-scale software development projects, they need
to be broken down into more manageable project components. With this thinking
we are going to begin our project by clearly mapping out the life of the project and
how we intend to follow all the deadlines and goals.

Before we begin the project, I must first phase the project and that begins by looking
at the user requirements we have been tasked with by the client. The term "user
requirements" refers to exactly what it sounds like. They are the end user's
requirements. These specifications specify how a facility, piece of equipment, or
process should perform in terms of the product to be manufactured, required
throughput, and manufacturing conditions.
However, the reason we are dividing the project into smaller tasks is so that a set task
can correspond to each and every stage of the methodology. In our case it will be
labelled an “agile sprint”, this may or may not be a collection of tasks but will be
decided at a later of date. I already analyzed extensively the project life cycle in
learning Aim A but will now look into in context of my current project.

, lOMoARcPSD|3013804




Project concept initiation – During this phase, which is currently ongoing, I as
the head of project management will summarize all the costs, benefits, user
requirements and requests with the feedback from the client and all stakeholders
who have input on this project. I will carry out this phase, through many different
means:

Identifying stakeholders

A project scope meeting

Breaking down requirements into smaller non-functional requirements

Acceptance of requirements documentation

Budgetary requirements

Risks and constraints

Project Initiation document

All of these documents/feedback will provide adequate information and scope for
stakeholders and product owner to give the greenlight for the project by highlighting the
requirements and constraints needed.

Definition and planning -

During the definition and planning stage we must get on with the tasks at hands as it
is an imperative part of the project life cycle and will most definitely be integrated
within our use of the agile methodology for the software production. It will be a
phase of continuation from the concept initiation including some important
documents that will most definitely be needed to produce in this stage:

 Scope and Budget (further developed from the initial documents)
 Work breakdown and schedule
 Gantt Chart
 Communication Plan
 Risk Management (in more depth)

Launch and Execution –

Although concept gathering and planning is an important step for every project and
its development it is not the be all and end all of project management and the
software development. The execution of all the hard work put into the planning is
just as if not more important than the processes before it with this in mind I have put
in steps to place more importance on the execution phase for example:




PAGE 1

, lOMoARcPSD|3013804




 Placing importance on status and tracking to make sure all targets are met
 Key performance indicators and using a range of different software’s
 Quality indicators (How the quality of the software is reflected)
 Forecasts

Performance and control –

As contracted for EBITS I must do all that is possible to ensure quality and
performance of the project and making sure that all workers are working at full
capacity, we can achieve this through a variety of ways, but one key aspect is
incentives and deliverables. By setting realistic and attainable targets with the
addition of incentives it boosts output and morale for workers, other things we will do
to accomplish this:

 Objectives (making them realistic and attainable to not strain workers)
 Quality deliverables
 Effort & cost tracking
 Performance (vague but an essential tool to look at)

Project Close -

We must ascertain to keep stakeholders and clients at EBITS happy as I am
contracted to them and the project must serve the purpose, with this in mind
producing a solid project closure. We will hold an immediate reflection meeting
called the “postmortem” to reflect on the failures and successes of the project and
complete all the needed documents:

 In depth postmortem
 Project punchline
 Reporting



Project scope meeting
Initial email to all EBITS




PAGE
2

, lOMoARcPSD|3013804




Conclusion of meetings
As seen by the meetings above the stakeholders and product owners accepted the initial
specification documentations relating to the user requirements, feasibility, cost
management of the project. However, there were some concerns raised about some user
requirements that were not being given enough importance which is a genuine and
rightful remark to make by the client. To address that allegation, we are sorting all the
user requirements into non-functional and functional to split them into smaller and more
manageable tasks.

User Requirements

Functional Requirements: These are the basic features that the system should provide
that the end user specifically requests. As part of the contract, all these functionalities
must be incorporated into the system. These are represented or stated as input to be
given to the system, operation to be performed, and expected output. They are the
user's stated requirements that, unlike non-functional requirements, can be seen
directly in the final product.

Non-functional requirements are the quality constraints that the system must meet to
meet the project contract's requirements. The importance of these factors, as well as the
extent to which they are implemented, varies by project. Non-behavioral
requirements is another name for them.

User Requirements
Table
Functional Non- Functional

Authentication Usability

Audit tracking Legal Requirements
As we are using
External interfaces Reliability the agile
methodology most
Historical Data Performance if not all the
requirements will
Reporting Requirements Subjective and
be in written
form.

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
AcademicAssignments University of Phoenix
View profile
Follow You need to be logged in order to follow users or courses
Sold
629
Member since
6 year
Number of followers
453
Documents
1069
Last sold
4 weeks ago

Help in all Courses Dq's, Assignments and MCQs, Midterm & Final Exams Experience: 15 Years in the online teaching field.

3.8

86 reviews

5
42
4
16
3
12
2
5
1
11

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these revision notes.

Didn't get what you expected? Choose another document

No problem! You can straightaway pick a different document that better suits what you're after.

Pay as you like, start learning straight away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and smashed it. It really can be that simple.”

Alisha Student

Frequently asked questions