Practice Questions with Answers & Detailed Rationales, NYC
Building Code Chapter 33, Construction and Demolition Safety,
Inspections, Hazard Prevention, Emergency Procedures &
Regulatory Compliance
Question 1
Which NYC Department of Buildings classification triggers the requirement for a licensed Site
Safety Manager on a construction project?
A. Any building over 4 stories in height
B. A major building, defined as 7 or more stories, 75 feet or more in height, or a footprint of
100,000 square feet or more
C. Any building with a footprint exceeding 50,000 square feet
D. Only buildings over 200 feet in height regardless of footprint
Correct Answer: B
Explanation: As of December 11, 2024, a major building is defined as 7 or more stories, 75
feet or more in height, or a 100,000 square foot footprint .
Question 2
,A Site Safety Manager discovers a crane operating on site without a required permit, and the
operator refuses to stop. What is the Site Safety Manager‘s immediate obligation under the
NYC Building Code?
A. Document the observation and address it at the next weekly safety meeting
B. Immediately notify the Department of Buildings directly
C. Shut down the crane personally by removing the keys
D. Wait for the construction superintendent to take action
Correct Answer: B
Explanation: The SSM must immediately notify the Department when equipment operates
without a permit and the operator refuses to desist .
Question 3
Under which circumstance is a Site Safety Manager NOT required to be present at a major
building site during active work?
A. During concrete placement operations
B. While workers are performing finish troweling of concrete floors
C. During structural steel erection
D. While exterior scaffolding is being installed
Correct Answer: B
Explanation: Presence is not required during finish troweling of concrete floors provided no
other work is in progress .
,Question 4
A primary Site Safety Manager has delegated several required site safety inspections to a
certified Site Safety Coordinator. What additional obligation does the primary SSM retain?
A. No additional obligations; delegation transfers all responsibility
B. The primary SSM must still perform separate spot checks throughout the day
C. The primary SSM need only review the SSC’s written reports
D. The primary SSM may delegate spot checks as well
Correct Answer: B
Explanation: Even when delegating inspections, the primary SSM must personally perform
separate spot checks throughout the day .
Question 5
Which individual is authorized to perform enumerated site safety inspections at a major
building where a primary Site Safety Manager is designated?
A. Any competent person designated by the contractor
B. An SST-trained worker with five years of experience
C. A certified Site Safety Coordinator designated by the SSM
D. The construction superintendent
Correct Answer: C
Explanation: Enumerated inspections may be delegated to certified Site Safety Coordinators
at any major building .
, Question 6
A concrete safety manager on a job site must coordinate directly with which individual
during concrete operations?
A. The concrete supplier’s dispatcher
B. The designated site safety manager or site safety coordinator
C. The crane operator
D. The owner‘s insurance representative
Correct Answer: B
Explanation: The concrete safety manager must coordinate directly with the designated SSM
or SSC on the job site .
Question 7
Which document must the construction superintendent review and sign before the start of
the subsequent work day?
A. The contractor’s payroll records
B. The concrete delivery tickets
C. The previous day’s entries in the site safety log
D. The crane operator’s log book
Correct Answer: C