Construction Coordinator I-II
Career Progression Examination
Summary Progression: Answered Correctly
Total Questions 130 Multiple Choice
Sections 10 Domain Areas
Format 75% Scenario-Based, 25% Direct Recall
Cognitive Mix 30% Recall / 50% Application / 20% Analysis
Edition 2026/2027 Construction Management Practice
Audience Construction Coordinator I-II Career Progression
This examination assesses competency across the Construction Coordinator I and II
career progression framework. Each question is provided with a verified correct answer
and a detailed rationale grounded in industry standards, contract administration
requirements, OSHA regulations, and practical field application. Questions emphasize
decision-making scenarios that differentiate Coordinator I (supervised documentation
and field support) from Coordinator II (independent trade coordination, change-order
pricing, and field supervision) responsibilities.
2026/2027 Construction Management Practice | 130 Questions Page 1
,Construction Coordinator I-II Career Progression Examination Summary Progression | Answered Correctly
Examination Contents
This examination contains 130 questions organized into 10 sections covering the Construction
Coordinator I-II competency domains. Each section below lists the question range and the subject
focus.
# Section Questions Subject Focus
1 Construction Fundamentals and Industry
Q1Overview
- Q15 (15 Q) Construction Types, Project Delivery Methods, & Ind
2 Construction Documents and Contract Administration
Q16 - Q32 (17 Q) Blueprints, Specifications, RFIs, Submittals, & Chang
3 Estimating, Bidding, and Cost Management
Q33 - Q50 (18 Q) Quantity Takeoff, Unit Pricing, Budgeting, & Cost Co
4 Project Scheduling and Planning Q51 - Q66 (16 Q) CPM, Gantt Charts, Milestones, & Schedule Updates
5 Site Supervision and Field Operations Q67 - Q82 (16 Q) Daily Reports, Site Logistics, Coordination, & Produc
6 Safety, OSHA Compliance, and Risk Management
Q83 - Q96 (14 Q) OSHA Standards, Toolbox Talks, JHA, & Incident Rep
7 Quality Control and Quality Assurance Q97 - Q108 (12 Q) Inspections, Punch Lists, Testing, & Commissioning
8 Procurement, Subcontractors, and Materials
Q109Management
- Q118 (10 Q) Procurement, Subcontracts, & Material Tracking
9 Communication, Leadership, and Stakeholder
Q119 - Management
Q125 (7 Q) Communication, Meetings, & Conflict Resolution
10 Professional Practice, Ethics, and CareerQ126
Progression
- Q130 (5 Q) Ethics, Documentation, & Coordinator I vs. II Respon
Cognitive Level Distribution Description
Recall 30% Direct recall of construction principles, regulations, and documentation standards
Application 50% Apply principles to realistic construction coordinator scenarios
Analysis 20% Analyze multi-factor situations and select the best course of action
2026/2027 Construction Management Practice | 130 Questions Page 2
,Construction Coordinator I-II Career Progression Examination Summary Progression | Answered Correctly
Section 1: Construction Fundamentals and Industry Overview
Subject Focus: Construction Types, Project Delivery Methods, & Industry Roles | Questions: Q1 - Q15 (15
questions)
Q1: A construction coordinator is reviewing a project for a 24-story mixed-use building
containing retail on the first three levels and residential units above. Which construction
type classification BEST describes this project?
A. Residential only, since the majority of floors are dwelling units
B. Commercial only, because retail occupancies drive code requirements
C. Mixed-use commercial/residential, requiring separation per IBC mixed-occupancy
provisions [CORRECT]
D. Industrial, because mixed occupancies automatically trigger industrial classification
Correct Answer: C
Rationale: A building combining retail (Mercantile Group M) and residential (Residential Group R)
occupancies is classified as mixed-use and must comply with IBC mixed-occupancy separation provisions
(either separated, non-separated, or accessory occupancy). Options A and B incorrectly reduce the
classification to a single use, while D is wrong because industrial (Group F/H) classification applies to
manufacturing and hazardous occupancies, not retail/residential combinations.
Q2: An owner wants to fast-track a hospital expansion by overlapping design and
construction phases so that foundation work can begin while interior finishes are still being
designed. Which project delivery method should the coordinator recommend?
A. Design-Bid-Build, because it provides the lowest lump-sum price
B. Construction Management at Risk (CMAR), which permits phased work packages under a
guaranteed maximum price [CORRECT]
C. Design-Bid-Build with multiple prime contractors
D. Job-order contracting (JOC)
Correct Answer: B
Rationale: CMAR allows the construction manager to act as a consultant during design and then convert
to a GC at risk, enabling fast-tracking through sequential work packages under a GMP. Design-Bid-Build
(A) requires complete documents before bidding, preventing overlap. Multiple prime DBB (C) creates
coordination burdens without overlap benefits. JOC (D) is for repetitive maintenance work, not major new
construction.
2026/2027 Construction Management Practice | 130 Questions Page 3
, Construction Coordinator I-II Career Progression Examination Summary Progression | Answered Correctly
Q3: Under a Design-Build (DB) delivery method, what is the contractual relationship
between the owner and the design team?
A. The owner contracts separately with the architect and the GC, with the architect serving as
the owner's representative
B. There is no direct contractual relationship; the design team is a subcontractor of the
design-builder [CORRECT]
C. The owner retains the architect as a direct consultant for peer review only
D. The architect acts as the agent of the owner for code compliance
Correct Answer: B
Rationale: In Design-Build, the owner executes a single contract with the design-builder, who then
employs the design team as a subcontractor. The owner has no privity of contract with the
architect/engineer. Option A describes CMAR or DBB. Option C is incorrect because peer review is
optional and not a structural feature. Option D describes traditional architect responsibilities under DBB,
not DB.
Q4: Which of the following is a CORRECT comparison of Construction Coordinator I versus
Construction Coordinator II responsibilities under typical career progression guidelines?
A. Coordinator I independently manages multiple concurrent projects; Coordinator II assists
with documentation only
B. Coordinator I performs routine field reports and submittal logs under supervision;
Coordinator II independently manages subcontractor coordination and change-order
pricing for assigned scopes [CORRECT]
C. Coordinator I approves all pay applications; Coordinator II prepares daily reports
D. Coordinator I and Coordinator II have identical scope, differing only in years of tenure
Correct Answer: B
Rationale: Career progression frameworks distinguish Coordinator I (entry-level, supervised tasks such
as daily reports, submittal tracking, RFI logging) from Coordinator II (independently manages trade
coordination, change-order pricing, and field supervision for assigned scopes). Option A reverses the
roles. Option C reverses the responsibility tiers. Option D ignores the substantive scope differences that
define the two levels.
Q5: A coordinator is orienting a new hire to the four major construction sectors. Which
project BEST represents the Infrastructure sector?
A. A 200,000 sq ft regional distribution warehouse
B. A 12-mile highway widening including bridges and storm drainage [CORRECT]
C. A 400-bed acute-care hospital tower
D. A 60-unit townhome subdivision
Correct Answer: B
Rationale: Infrastructure (heavy civil) includes highways, bridges, tunnels, water/wastewater systems,
and other public works. Option A is commercial/industrial. Option C is institutional (commercial subset).
Option D is residential. Only B fits the infrastructure classification.
2026/2027 Construction Management Practice | 130 Questions Page 4