PMT 3600V Exam 2: Complete Q&A
Study Guide/PMT 3600V Exam
2|Questions and Answers|Latest Update
with complete solution
This guide provides a comprehensive set of questions and answers
covering key topics for the PMT 3600V Exam 2, based on the DAU
Program Management Office course curriculum. The questions are
organized by topic and include detailed rationales to support your
study.
Section 1: Scheduling, WBS, and Integrated Master
Plan/Schedule
Question 1
What is the primary purpose of a Work Breakdown Structure (WBS) in
program management?
A. To list the team members
B. To break the total program scope into deliverable-oriented pieces
C. To show only the schedule
D. To estimate profit
,Correct Answer: B
Rationale: The WBS breaks 100% of the work into smaller, manageable
products and tasks so you don't miss anything. It is product-oriented
and ensures complete scope coverage.
Question 2
What is the difference between a Program WBS and a Contract WBS?
A. They are the same
B. Program WBS is for the contractor only
C. Program WBS is the total government program; Contract WBS is
only the part on contract
D. Contract WBS is always larger
Correct Answer: C
Rationale: The Program WBS covers the entire government program
scope. The Contract WBS is the slice the contractor is responsible for
delivering under the contract.
Question 3
What is the Integrated Master Plan (IMP)?
A. A detailed schedule with dates
B. An event-based plan that lists accomplishments and criteria
C. A budget document
D. A risk list
Correct Answer: B
, Rationale: The IMP is an event-based plan that defines WHAT must
happen through a hierarchy of events, accomplishments, and criteria.
It contains NO dates.
Question 4
What is the Integrated Master Schedule (IMS)?
A. The same as the IMP
B. The time-phased, detailed schedule that executes the IMP
C. A parts list
D. A leadership chart
Correct Answer: B
Rationale: The IMS is the execution of the IMP. It takes the IMP and
adds who, how long, dependencies, and dates to create a
time-phased, detailed schedule.
Question 5
Which statement is true about the IMP and IMS relationship?
A. IMS drives IMP
B. IMP drives IMS
C. They are unrelated
D. IMP comes after IMS
Correct Answer: B
Rationale: You define what needs to be done in the IMP first, then you
schedule it in the IMS. The IMP drives the IMS, not the reverse.
Study Guide/PMT 3600V Exam
2|Questions and Answers|Latest Update
with complete solution
This guide provides a comprehensive set of questions and answers
covering key topics for the PMT 3600V Exam 2, based on the DAU
Program Management Office course curriculum. The questions are
organized by topic and include detailed rationales to support your
study.
Section 1: Scheduling, WBS, and Integrated Master
Plan/Schedule
Question 1
What is the primary purpose of a Work Breakdown Structure (WBS) in
program management?
A. To list the team members
B. To break the total program scope into deliverable-oriented pieces
C. To show only the schedule
D. To estimate profit
,Correct Answer: B
Rationale: The WBS breaks 100% of the work into smaller, manageable
products and tasks so you don't miss anything. It is product-oriented
and ensures complete scope coverage.
Question 2
What is the difference between a Program WBS and a Contract WBS?
A. They are the same
B. Program WBS is for the contractor only
C. Program WBS is the total government program; Contract WBS is
only the part on contract
D. Contract WBS is always larger
Correct Answer: C
Rationale: The Program WBS covers the entire government program
scope. The Contract WBS is the slice the contractor is responsible for
delivering under the contract.
Question 3
What is the Integrated Master Plan (IMP)?
A. A detailed schedule with dates
B. An event-based plan that lists accomplishments and criteria
C. A budget document
D. A risk list
Correct Answer: B
, Rationale: The IMP is an event-based plan that defines WHAT must
happen through a hierarchy of events, accomplishments, and criteria.
It contains NO dates.
Question 4
What is the Integrated Master Schedule (IMS)?
A. The same as the IMP
B. The time-phased, detailed schedule that executes the IMP
C. A parts list
D. A leadership chart
Correct Answer: B
Rationale: The IMS is the execution of the IMP. It takes the IMP and
adds who, how long, dependencies, and dates to create a
time-phased, detailed schedule.
Question 5
Which statement is true about the IMP and IMS relationship?
A. IMS drives IMP
B. IMP drives IMS
C. They are unrelated
D. IMP comes after IMS
Correct Answer: B
Rationale: You define what needs to be done in the IMP first, then you
schedule it in the IMS. The IMP drives the IMS, not the reverse.