CLM 059 UPDATED ACTUAL EXAM QUESTIONS AND CORRECT ANSWERS

Document preview thumbnail
Preview 3 out of 19 pages

CLM 059 UPDATED ACTUAL EXAM QUESTIONS AND CORRECT ANSWERS

Content preview

CLM 059 UPDATED ACTUAL EXAM
QUESTIONS AND CORRECT ANSWERS

●● Which of the following are typical sources of framing assumptions
(FAs)? (Select all that apply.)
Answer: -Technological and engineering challenges
-Interdependencies with other programs
-Cost, schedule, and requirements tradeoffs


●● During which phase should you be building and maintaining robust
stakeholder relationships and ensuring horizontal and vertical
communications?
Answer: MSA, TMRR, EMD


●● What would be the appropriate corrective action for the following
issue: One of the orders for materials is going to run 75% over budget
because the order will have to be shipped by air to meet schedule
requirements. The budgeting team may be able to find funds from other
sources.
Answer: Transfer


●● Which of the following is a responsibility of the Integrated Product
Team (IPT) during the risk management (RM) process?
Answer: Coordinate RM efforts for risks affecting multiple IPTs.

,●● What is the main differences between a risk and an opportunity?
Answer: Risks have a negative consequence, while opportunities
requires creating additional tasks.


●● A Monte Carlo simulation reports a 75% chance that the prototyping
tasks associated with a new Doppler-based wind measuring technology
will be delayed 17 business days due to supply shortages of two key
pieces of equipment. Based on the likelihood and consequence table,
which of the following represents the appropriate location on the risk
matrix?
Answer: L = 4; C = 2


●● During Technology Maturation and Risk Reduction (TMRR), the
goal is to primarily reduce which types of risk? (Select all that apply.)
Answer: -Technology
-Integration
-Engineering


●● Based on the results of a simulation, there is a 70% chance that the
project will end two weeks behind schedule. Using the table provided,
what would the cumulative schedule risk be, based on a two-week
schedule delay?
Answer: Probability 4; Schedule Impact 2

, ●● Which of the following is the difference between a risk and an issue?
Answer: A risk is the potential of occurring; and issue has occurred or is
certain to occur.


●● Which of the following is a critical success factor to ensure effective
risk management (RM)?
Answer: -Program Risk Process (PRP) Document


●● Who may write the Program Risk Process (PRP) Document?
Answer: The program manager (PM) or a dedicated risk manager


●● The following describes which type of category of risk: Certification
for a new weapons system is scheduled for January. The test is
dependent on temperatures below freezing. If the temperature is too
warm, the system cannot be certified.
Answer: Business


●● Your program is developing a piece of equipment that require a
seismograph to identify and track low ground vibrations within a
specific range. You need to understand how well the design and
manufacturing process will be able to meet the performance goals.
Which tool will provide that information?
Answer: Performance risk analysis (PRA)

Document information

Uploaded on
August 4, 2026
Number of pages
19
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
£12.83

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
FocusFile7
3.9
(24)
Sold
231
Followers
3
Items
60822
Last sold
12 hours ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these revision notes.

Didn't get what you expected? Choose another document

No problem! You can straightaway pick a different document that better suits what you're after.

Pay as you like, start learning straight away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and smashed it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions