True or False? A labor laws placard must be posted. True
True or False? The GC shall ensure that all subcontractors True
and their workers have secured, maintained, and
complied with all required licenses, permits and
certificates relating to, or otherwise necessary or
appropriate for, the performance and completion of the
work and all other activities and obligations under the
Contract Documents.
Which of the following is required to be present at the All of the above
job site?
A. Safety Manual and up to date MSDS binder
B. SWPP certificate posted
C. Visitors sign in book
D. All of the Above
, The SWPP implementation sequence may be modified? After consulting with the project SWPP Designer (CEC) and, if required, the
Project Owner and receiving written approval.
True or False: the GC doesn't need to worry about access False
control after possession.
When installing perimeter BMP controls: Note locations and dates of installation on the site map.
A SWPP Site Map will show all of the following except: B. Notices of Violation C
A. Locations of BMPs
B. Notices of Violation
C. Phasing and Sequence
D. Limits of Disturbance
In what circumstances must your company run newly Any new hire employees who will provide services to Walmart in a mandatory E-
hired employees through E-Verify? Verify State: AL, AZ, GA, LA, MS, NC, SC, TN or UT.
Factors to consider when creating your schedule include: Account for the time it takes to install or implement BMP's between each phase of
construction
Which of the following is not a silt fence related C. Trackout
deficiency?
A. Tears or holes in the fabric
B. Excessive sediment accumulation
C. Track out
D. Undercutting
Requirements for managing stormwater activity on a NPDES
construction site are outlined in the following regulation:
True or False: Subcontractors do not need a GC badge False
during the first week of construction as this is the slowest
time of the project.
Runoff Controls include all but which of the following: A. Rolled erosion control products
A. Rolled erosion control products
B. Diversions
C. Check dams
D. Slope drains
To reduce the possibility of undercutting in channels, you Install filter fabric under rock and similar materials placed within the stormwater
should: conveyance