The following must be marked on Site Maps in job site The dates when BMP changes or additions take place
trailer as work progresses.
the best location for portable toilets on your on level ground in low construction traffic areas
construction site is...
The SWPPP implementation sequence may be modified.... after consulting with the project SWPPP designer (CEC) and, if required, the
project owner and receiving written approval.
True or false: The superintendent is responsible for True
keeping current contact list of all parties involved with
the project.
Storm drain inlet PROTECTION is often intended to... retain large quantities of sediment.
, why is vegetation an important method for controlling -to increase water infiltration
erosion? -roots reinforce soil
-dissipates rainfall energy
when installing and maintaining a check dam make sure... the low point (overflow) of the check dam is in the middle of the channel
which of the following is NOT a beneficial use of water? flushing a spill down a storm drain
of the following, which is a primary erosion control minimize the extent and duration of soil exposure-stabilize disturbed areas
objective? quickly.
soil stockpiles and other disturbed areas must receive... temporary stabilization if they will remain inactive for more than 14 days and
potentially fewer days depending on the jurisdiction.
in addition to worker verification and badging, what other immigration,E-verify, wages, harassment, discrimination and, joint employment.
employment incidents and/or regulatory contacts may
happen?
a fiber roll or wattle is intended to... capture sediment from slope and slow runoff velocity
runoff controls include all but which one of the rolled erosion control products
following..
the notice of termination can be filed when all construction activity, inside and outside the building, is complete and
permanent stabilization has been verified as adequate to meet permit
requirements.
a key first step before installing a rolled erosion control properly preparing the ground surface
product or RECP is
proper spill management should include all of the installation of a spill pit on your construction site
following except
true or false: contractor shall at all time keep just and true true
books, records and accounts at its facility showing the
actual cost and expenses that contractor incurs in
connection with the work, owner or its duly authorized
representative shall have the right, during term of this
contract and for two years after the earlier of the
completion of the work or termination of this contract, to
enter onto contractors facility to examine and audit the
books, records and accounts that pertain to this contract.