Leed Certification fees are based on:
a. Project gross floor area
b. project complexity
c. project cost.
d. the number of review submissions - ANSWER a. Project gross floor area
What is not true about innovation (ID) credits?
a. Each innovation credit awarded requires a 12 month follow up to verify the strategy is
comprehensive.
b. ID credits are awarded for environmental impacts.
c. ID credits can be awarded for specific environmental issues related to the region where
the project is located.
d. exemplary performance is only available for existing LEED credits. - ANSWER a. Each
innovation credit awarded requires a 12 month follow up to verify the strategy is compre-
hensive.
When can a project register for LEED Certification?
a. In Schematic Design
b. Prior to construction completion
c. Anytime
d. Before design is complete - ANSWER d. Before design is complete
1
,When should a project submit design documentation to the USGBC for review?
a. As each project team member completes his/her documentation
b. Before design is complete.
c. Before construction begins.
d. Before LEED online is activated - ANSWER c. Before construction begins.
The criteria to be nominated as a LEED Fellow does not include:
a. LEED AP with specialty (in good standing)
b. LEED Professional for ten years
c. Ten or more years of professional green building experience.
d. The nominee must pay an application fee. - ANSWER b. LEED Professional for ten years
How many Regional Priority points may a project earn?
a. 2
b. 3
c. 4
d. 6 - ANSWER c. 4
When submitting design phase credits in the Split Review, Which of the following represent
possible review responses issued by the USGBC? (Choose two)
a. Pending
b. Denied
c. Anticipated
2
, d. Approved
e. Awarded
f. Achieved - ANSWER b. Denied
c. Anticipated
What information is required to register a project for LEED certification? (Choose three)
a. List of LEED project team members
b. Name of LEED-AP who will be working on the project
c. Primary contact information (Agent and Project Administrator)
d. Project owner information
e. Project type - ANSWER c. Primary contact information (Agent and Project Administra-
tor)
d. Project owner information
e. Project type
Which of the following statements are true regarding Formal Inquiries? (Choose two)
a. They may only reference one credit.
b. They may not include plans or drawings
c. They must be submitted with the LEED application.
d. They may not be longer than 6,000 characters (including spaces) - ANSWER a. They
may only reference one credit.
b. They may not include plans or drawings
During the construction review, design credits that were ruled as "Anticipated" are awarded
in which of the following are true? (Choose two)
a. All design credit documentation is resubmitted
3
a. Project gross floor area
b. project complexity
c. project cost.
d. the number of review submissions - ANSWER a. Project gross floor area
What is not true about innovation (ID) credits?
a. Each innovation credit awarded requires a 12 month follow up to verify the strategy is
comprehensive.
b. ID credits are awarded for environmental impacts.
c. ID credits can be awarded for specific environmental issues related to the region where
the project is located.
d. exemplary performance is only available for existing LEED credits. - ANSWER a. Each
innovation credit awarded requires a 12 month follow up to verify the strategy is compre-
hensive.
When can a project register for LEED Certification?
a. In Schematic Design
b. Prior to construction completion
c. Anytime
d. Before design is complete - ANSWER d. Before design is complete
1
,When should a project submit design documentation to the USGBC for review?
a. As each project team member completes his/her documentation
b. Before design is complete.
c. Before construction begins.
d. Before LEED online is activated - ANSWER c. Before construction begins.
The criteria to be nominated as a LEED Fellow does not include:
a. LEED AP with specialty (in good standing)
b. LEED Professional for ten years
c. Ten or more years of professional green building experience.
d. The nominee must pay an application fee. - ANSWER b. LEED Professional for ten years
How many Regional Priority points may a project earn?
a. 2
b. 3
c. 4
d. 6 - ANSWER c. 4
When submitting design phase credits in the Split Review, Which of the following represent
possible review responses issued by the USGBC? (Choose two)
a. Pending
b. Denied
c. Anticipated
2
, d. Approved
e. Awarded
f. Achieved - ANSWER b. Denied
c. Anticipated
What information is required to register a project for LEED certification? (Choose three)
a. List of LEED project team members
b. Name of LEED-AP who will be working on the project
c. Primary contact information (Agent and Project Administrator)
d. Project owner information
e. Project type - ANSWER c. Primary contact information (Agent and Project Administra-
tor)
d. Project owner information
e. Project type
Which of the following statements are true regarding Formal Inquiries? (Choose two)
a. They may only reference one credit.
b. They may not include plans or drawings
c. They must be submitted with the LEED application.
d. They may not be longer than 6,000 characters (including spaces) - ANSWER a. They
may only reference one credit.
b. They may not include plans or drawings
During the construction review, design credits that were ruled as "Anticipated" are awarded
in which of the following are true? (Choose two)
a. All design credit documentation is resubmitted
3