• Wrong document? Swap it for free
  • Written by students who passed
  • Immediately available after payment
  • Read online or as PDF
Sell
Where do you study
Your language
Start selling Create your account
Document preview thumbnail
Preview 3 out of 18 pages
Exam (elaborations)

Cisa Exam-Information Systems Acquisitions ,Development And Implementation 2026|Verified Questions And 100% Correct Solutions|Updated Version !!!|A+ Graded|Exam Ready|95% Success Rate

Document preview thumbnail
Preview 3 out of 18 pages

CISA EXAM-INFORMATION SYSTEMS ACQUISITIONS, DEVELOPMENT, AND IMPLEMENTATION 2026|VERIFIED QUESTIONS AND 100% CORRECT SOLUTIONS|UPDATED VERSION !!!|A+ GRADED|EXAM READY|95% SUCCESS RATE This title is comprehensive, highlighting the document's key features and benefits for CISA exam preparation. It includes: * Specific Exam Focus: Clearly indicates the exam area (Information Systems Acquisitions, Development, and Implementation) and the year (2026). * Value Proposition: Emphasizes verified questions, correct solutions, updated content, top grades, exam readiness, and a high success rate. * Keywords: Uses relevant keywords to make the document easily searchable.

Content preview

ACQUISITIONS ,DEVELOPMENT AND

AND 100% CORRECT SOLUTIONS|UPDATED
VERSION !!!|A+ GRADED|EXAM READY|95%

Many IT projects experience problems because the development time and/or resource
requirements are underestimated. Which of the following techniques provides the
GREATEST assistance in developing an estimate of project duration? -
ANSWER Program evaluation review technique chart



This will help determine project duration once all the activities and the work involved with
those activities are known



The use of object-oriented design and development techniques would MOST likely: -
ANSWER facilitate the ability to reuse modules.



One of the major benefits of object-oriented design and development is the ability to reuse
modules



Which of the following should be included in a feasibility study for a project to implement an
electronic data interchange process? - ANSWER The necessary communication
protocols



The communications protocols must be included because there may be significant cost
implications if new hardware and software are involved, and risk implications if the
technology is new to the organization.




1

,A company has implemented a new client-server enterprise resource planning (ERP) system.
Local branches transmit customer orders to a central manufacturing facility. Which of the
following would BEST ensure that the orders are processed accurately, and the
corresponding products are produced? - ANSWER Verifying production of customer
orders



Verification of the products produced will ensure that the produced products match the
orders in the order system.



Once an organization has finished the business process reengineering (BPR) of all its critical
operations, lan IS auditor would MOST likely focus on a review of: - ANSWER post-BPR
process flowcharts



An IS auditor's task is to identify and ensure that key controls have been incorporated into
the reengineered process.



When reviewing a project where quality is a major concern, an IS auditor should use the
project management triangle to explain that: - ANSWER Increases in quality can be
achieved, if resource allocation is decreased



The three primary dimensions of a project are determined by the deliverables, the allocated
resources and the delivery time. The area of the project management triangle, comprised of
these three dimensions, is fixed. Depending on the degree of freedom, changes in one
dimension might be compensated by changing either one or both remaining dimensions.
Thus, if resource allocation is decreased, an increase in quality can be achieved if a delay in
the delivery time of the project will be accepted. The area of the triangle always remains
constant.



Documentation of a business case used in an IT development project should be retained
until: - ANSWER The end of the system's life cycle



A business case can and should be used throughout the life cycle of the product. It serves as
an anchor for new (management) personnel, helps to maintain focus and provides valuable
information on estimates versus actuals. Questions such as "Why do we do that?", "What

2

, was the original intent?", and "How did we perform against the plan?" Can be answered,
and lessons for developing future business cases can be learned.



During the review of a web-based software development project, an IS auditor realizes that
coding standards are not enforced, and code reviews are rarely carried out. This will MOST
likely increase the likelihood of a successful: - ANSWER Buffer overflow



Poorly written code, especially in web-based applications, is often exploited by hackers using
buffer overflow techniques



When identifying an earlier project completion time, which is to be obtained by paying a
premium for early completion, the activities that should be selected are those: -
ANSWER That have zero slack time



A critical path's activity time is longer than that for any other path through the network. This
path is important because if everything goes as scheduled, its length gives the shortest
possible completion time for the overall project. Activities on the critical path become
candidates for crashing (i.e, for reduction in their time by payment of a premium for early
completion). Activities on the critical path have zero slack time and conversely, activities with
zero slack time are on a critical path. By successively relaxing activities on a critical loath, a
curve showing total project costs versus time can be obtained.



Which of the following should an IS auditor review to understand project progress in terms
of time, budget and deliverables for early detection of possible overruns and for projecting
estimates at completion? - ANSWER Earned value analysis



This is an industry standard method for measuring a projects progress at any given point in
time, forecasting its completion date and final cost, and analyzing variances in the schedule
and budget as the projects proceeds. It compares the planned amount of work with what
has actually been completed to determine if the cost, schedule and work accomplished are
progressing in accordance with the plan. EVA works most effectively if a well-informed work
breakdown structure exists.




3

Document information

Uploaded on
February 20, 2026
Number of pages
18
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
£11.11

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
THESTUDYVAULT
3.4
(20)
Sold
157
Followers
6
Items
14231
Last sold
2 days ago




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these revision notes.

Didn't get what you expected? Choose another document

No problem! You can straightaway pick a different document that better suits what you're after.

Pay as you like, start learning straight away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and smashed it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions