FINAL EXAM ELEVATOR



wrench used for rail installation - CORRECT ANSWER-spud wrench


The minimum clearance form the floor to the suspended ceiling is:
a. 80"
b. 96"
c. 7'3"
d. 8'2" - CORRECT ANSWER-a. 80"


what should you be aware of when removing a cab for replacement?
a. The weight that is to be removed from the ceiling.
b. The original weight and counterbalancing.
c. How much the cab was out of square.
d. Cover the panels so they do not get banged up. - CORRECT ANSWER-b. The
original weight and counterbalancing.


When fans are used on modernization jobs for exhausting fumes, what
statement is correct?
a. They're to keep you cool, not for exhausting fumes.
b. They should direct the fumes into the hoistway.
c. They should direct the fumes into the pit.
d. They should direct the fumes to the outside. - CORRECT ANSWER-d. They
should direct the fumes to the outside.


The star symbol is used on the COP for what?

,a. To show where the floor buttons are located.
b. To designate the main floor.
c. To make the door buttons stand out.
d. To show the alarm bell location. - CORRECT ANSWER-b. To designate the
main floor.


Using a laminate stop strip against the fence on a table saw:
a. Keeps the laminate straight to the blade.
b. Keeps the laminate from lifting off the blade.
c. Keeps the laminate from slipping under the fence.
d. Keeps the laminate from going over the fence. - CORRECT ANSWER-c. Keeps
the laminate from slipping under the fence.


The contact adhesives must be ________ before final bonding:
a. 85 degrees
b. Dry
c. Wet to touch
d. Cold - CORRECT ANSWER-b. Dry


What is the most important piece of equipment you have when using a power
saw?
a. Combination blade
b. Safety glasses
c. Wood rule
d. Framing square - CORRECT ANSWER-b. safety glasses


When using a circular saw, which of the following is correct?

,a. Never start the cut until the blade is turning full RPM
b. The base is not adjustable for cutting depth
c. Circular saw blades range from 10 to 16 inches
d. Remove the retractable guard before cutting - CORRECT ANSWER-a. Never
start the cut until the blade is turning full RPM


What is used to make crosscuts on a table saw?
a. Push stick
b. Rip fence
c. Miter gauge
d. Larger Blade - CORRECT ANSWER-c. Miter saw


When making crosscuts with a radial arm saw which statement is correct?
a. Push the wood slowly into the blade.
b. Restrain the blade from moving too fast.
c. Rotate and lock the blade parallel to the guide.
d. Adjust the blade 1/4" above to cutting surface - CORRECT ANSWER-b.
Restrain the blade from moving too fast


What are the two things a compound mitre saw does best at the same time?
a. moving it around and setting it up is fast.
b. You can cut left and right at the same time.
c. Tilting the blade 45 degrees and pivoting the table 45 degrees gives you a 90
degree square cut.
d. bevel and mitre cuts can be made at the same time - CORRECT ANSWER-d.
bevel and mitre cuts can be made at the same time

, Why do we use laminated glass in the walls of glass elevator cabs?
a. if the glass breaks you can get a replacement at the hardware store.
b. if the glass cracks the plastic interlayer holds the fragments
c. it is made in a variety of colors
d. it is easy to handle and installs quickly - CORRECT ANSWER-b. if the glass
cracks the plastic interlayer holds the fragments


Which of the following is NOT a step in preparing the walls before hanging
panels?
a. check walls for square and plumb
b. mount handrails on the walls where the panels will be installed.
c. clean surfaces and fill all holes not being used
d. preheat walls as per specifications - CORRECT ANSWER-b. mount handrails
on the walls where the panels will be installed


When installing a resilient tile floor covering, there should be a layer of
________ between the underlayment and the tiles.
a. plywood
b. grout
c. 15lb asphalt paper
d. tile separators - CORRECT ANSWER-c. 15 lb asphalt paper


While similar to laying resilient floor tiles, ceramic tiles require the additional
steps of:
a. grouting and sealing
b. stress testing and certification
c. glazing and firing
d. marking and cutting - CORRECT ANSWER-a. grouting and sealing

Dokument Information

Hochgeladen auf
17. oktober 2026
Anzahl der Seiten
33
geschrieben in
2026/2027
Typ
Prüfung
Enthält
Fragen & antworten
23,30 €

Falsches Dokument? Kostenlos tauschen Innerhalb von 14 Tagen nach dem Kauf und vor dem Herunterladen kannst du ein anderes Dokument wählen. Du kannst den Betrag einfach neu ausgeben.
Geschrieben von Student*innen, die bestanden haben
Sofort verfügbar nach Zahlung
Online lesen oder als PDF

Seller avatar
MadeItEasy
5,0
(1)
Verkauft
2
Anhänger
0
Sachen
528
Zuletzt verkauft
1 Jahren vor



Warum sich Studierende für Stuvia entscheiden

on Mitstudent*innen erstellt, durch Bewertungen verifiziert

Geschrieben von Student*innen, die bestanden haben und bewertet von anderen, die diese Studiendokumente verwendet haben.

Nicht zufrieden? Wähle ein anderes Dokument

Kein Problem! Du kannst direkt ein anderes Dokument wählen, das besser zu dem passt, was du suchst.

Bezahle wie du möchtest, fange sofort an zu lernen

Kein Abonnement, keine Verpflichtungen. Bezahle wie gewohnt per Kreditkarte oder Sofort und lade dein PDF-Dokument sofort herunter.

Student with book image

“Gekauft, heruntergeladen und bestanden. So einfach kann es sein.”

Alisha Student

Arbeitest du an deiner Quellenangabe?

Erstelle korrekte Quellenangaben in APA, MLA und Harvard mit unserem kostenlosen Zitiergenerator.

Arbeitest du an deiner Quellenangabe?

Häufig gestellte Fragen