FDOT Earthwork 2 quick questions with solutions ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//||
muck ✔✔A-8 Material ||\\//|| ||\\//||
LBR ✔✔Strength test of material based on standardized 800 psi
||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//||
Select ✔✔Material that can be used anywhere in the the embankment
||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//||
one ✔✔number of density log books per contact
||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//||
verification ✔✔testing done by department ||\\//|| ||\\//|| ||\\//|| ||\\//||
dry ✔✔blank density is the weight of solid should
||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//||
lot ✔✔a single lift of finished material
||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//||
cover zone ✔✔area from the bottom of the pipe to 12 inches above
||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//||
resolution ✔✔testing to resolve QC & VT differences ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//||
High Plastic ✔✔Material with LL greater than 50
||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//||
Wet Density ✔✔weight of soil and water
||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//||
Modified Proctor ✔✔Proctor usually used for subgrade and base. FM1-T180
||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//||
muck ✔✔A-8 Material ||\\//|| ||\\//||
LBR ✔✔Strength test of material based on standardized 800 psi
||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//||
Select ✔✔Material that can be used anywhere in the the embankment
||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//||
one ✔✔number of density log books per contact
||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//||
verification ✔✔testing done by department ||\\//|| ||\\//|| ||\\//|| ||\\//||
dry ✔✔blank density is the weight of solid should
||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//||
lot ✔✔a single lift of finished material
||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//||
cover zone ✔✔area from the bottom of the pipe to 12 inches above
||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//||
resolution ✔✔testing to resolve QC & VT differences ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//||
High Plastic ✔✔Material with LL greater than 50
||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//||
Wet Density ✔✔weight of soil and water
||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//||
Modified Proctor ✔✔Proctor usually used for subgrade and base. FM1-T180
||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//|| ||\\//||