100% tevredenheidsgarantie Direct beschikbaar na je betaling Lees online óf als PDF Geen vaste maandelijkse kosten 4.2 TrustPilot
logo-home
College aantekeningen

project management notes

Beoordeling
-
Verkocht
-
Pagina's
20
Geüpload op
09-10-2025
Geschreven in
2025/2026

summaries of each week's topic

Instelling
Vak










Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
Vak

Documentinformatie

Geüpload op
9 oktober 2025
Aantal pagina's
20
Geschreven in
2025/2026
Type
College aantekeningen
Docent(en)
Dr. kimberly marie deranek
Bevat
Alle colleges

Onderwerpen

Voorbeeld van de inhoud

Scheduling the Project

Purpose of a Schedule:
●​ Ensures the timely completion of a project
●​ Identifies what needs to get done and when
●​ Shows how all the pieces of the project fit together
●​ Team members see how their work affects others
●​ Used to monitor and control the project

Formats to create a Project Schedule:
●​ Gantt Charts
●​ Network Diagram
-​ PERT Network
-​ CPM Network


Network Diagrams
(Developed in the 1950s)
• Developed in the 1950’s
– A diagram of nodes and arrows (directional arcs)
– Illustrate the flow of activities
• Program Evaluation and Review Technique (PERT)
– U.S. Navy, Booz-Allen Hamilton, and Lockheed Aircraft
– Probabilistic activity durations (randomness)
– AOA
• Critical Path Method (CPM)
– Dupont De Nemours Inc.
– Deterministic activity durations (originally)
– AON


Event vs. Milestone
(0” duration – 0 hours or days)
Event
• An identifiable state
– Result of completing one or more activities
• Predecessor activities must be completed
Milestone
• Noteworthy event
• Marks significant progress

, Task Dependencies
(Precedence Diagram)
• Finish to Start
– Activity (predecessor) must finish before the successor can start.
– Dig hole – plant tree
• Start to Start
– Activity (predecessor) must start before the successor can start.
– Design code - code
• Finish to Finish
– Activity (predecessor) must finish before the successor can finish
– Test - documentation
• Start to Finish
– Activity (predecessor) must start before the successor can finish.
– Software cutover; new system implementation




An activity is an element of work that has:
– an expected duration
– a cost
– resource requirements
– predecessor
– successor
Sequencing Events (CPM)

, ●​ Path: A series of connected activities between two events (i.e. start/finish)
-​ Helps calculate Project Duration

Merge vs. Burst
Merge: An event which represents the joint completion of multiple activities.
Burst: An event which represents the beginning of multiple activities.



Critical Path

“Critical path”
-​ Series of activities (path) that determines the earliest time project can be completed
-​ Longest path through the network diagram
-​ Has the least amount of slack or float
What is Slack or Float?
-​ Amount of time an activity may be delayed without delaying project finish date
●​ Free – impacts successor
●​ Total – impacts total project

Critical Path Calculations
●​ First develop a good network diagram




●​ Add the duration estimates for all activities
●​ Calculated Early Start/Finish and Late Start/Finish/Slack
●​ The longest path is the critical path
-​ Activities have no slack
-​ If activities on the critical path slips, the whole project will be delayed
-​ Alerts PM to take corrective action

●​ Activities on all paths must be completed to finish the project
●​ The critical path is not the one with all the critical activities; it only accounts for time
●​ There can be more than one critical path if the lengths of two or more paths are the
same
●​ The critical path can change as the project progresses
€7,00
Krijg toegang tot het volledige document:

100% tevredenheidsgarantie
Direct beschikbaar na je betaling
Lees online óf als PDF
Geen vaste maandelijkse kosten

Maak kennis met de verkoper
Seller avatar
megangray1

Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
megangray1 Nova Southeastern University
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
Nieuw op Stuvia
Lid sinds
2 maanden
Aantal volgers
0
Documenten
8
Laatst verkocht
-

0,0

0 beoordelingen

5
0
4
0
3
0
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen