WILLOW ADMIN 1 ACTUAL EXAM \NEWEST VERSION
WITH COMPLETE QUESTIONS AND ACCURATE
DETAILED ANSWERS \LATEST UPDATE \ASSURED
PASS \GRADED A+ \BRAND NEW!!2025-2026
Which of the following is NOT a
part of the Construction
Manager's job?
a. Review contractors shop
drawings to validate
conformance with
contract
b. Work with designer to verify
quality &
progress of work c.Manage
change order process
d.Document specific activities
of trade contractors &
update network
schedule
What is a Punch List? c
a. A list of materials
needed for
procurement.
b. A summary of the project's
budget
c. A list of incomplete or
defective items to be
resolved before final
payment.
d. A schedule of design
milestones.
1/1
7
,7/8/25, 3:15 PM Exam 1 ADMIN
As built drawings, d
warranties, guarantees and
operations manual are all
provided to the owner
during which project
phase?
a. Design
b. Conceptual planning
c. Construction
d. Project closeout
Which of the following is NOT c
part of the preconstruction
phase?.
a.Conceptual Planning
b.Schematic Design
c.Bidding & Award
d. Design Development
True or False: A delivery True
method is a type of
contracting method.
What is substantial completion? a
a. The stage of a project
where the owner can
occupy/use the facility for
its intended purpose, even
with minor work remaining.
b. The stage of a project
where JHA is approved.
c. The stage of a project
where the owner receives
final payment and all
warranties begin.
d. The stage of a
project when all
inspections are
/ 2/1
7
, 7/8/25, 3:15 PM Exam 1 ADMIN
done.
During the design c
development phase, is that
one of the key
responsibilities of the
construction manager?
a. Approve shop
drawings for all
subcontractors
b. Identify long-lead materials
and
equipment for procurement c.
Prepare for permit
acquisition and submit
required reports
d. Finalize all construction
documents for the bid
package
What was the critical c
engineering failure that led
to the Hyatt Regency
walkway collapse?
a. A single hanger rod
snapped due to
corrosion
b. Electrical overload
caused an explosion in the
atrium
c. A redesign introduced a
/ 3/1
7