Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Document preview thumbnail
Voorbeeld 2 van de 9 pagina's
Tentamen (uitwerkingen)

Udemy Exam UPDATED ACTUAL Exam Questions and CORRECT Answers

Document preview thumbnail
Voorbeeld 2 van de 9 pagina's

Udemy Exam UPDATED ACTUAL Exam Questions and CORRECT Answers requirements documentation - CORRECT ANSWER - Your company has decided to roll out a new Wi-Fi network for the staff. The sponsor has informed you that encryption on the network is mandatory. Where will the project manager document that the encryption was mandated by the sponsor?

Voorbeeld van de inhoud

Udemy Exam UPDATED ACTUAL Exam
Questions and CORRECT Answers
requirements documentation - CORRECT ANSWER - Your company has decided to roll
out a new Wi-Fi network for the staff. The sponsor has informed you that encryption on the
network is mandatory. Where will the project manager document that the encryption was
mandated by the sponsor?


inform the team that six weeks is too long and they will need to decompose the feature into
smaller increments - CORRECT ANSWER - The business case is used to show the
benefits of the project. The project charter is used to authorize the project. The project
management plan outlines how to execute, monitor and control, and close the project. The
project benefits report is a made-up term.


meet with the project team members to understand why they feel the contractor has not been
doing the work in the contract - CORRECT ANSWER - There have been many disputes
on the project with the current contractor. The contractor claims the project team is always
asking that work not be listed in the contract, and the team claims that the contractor has not
been doing the work listed in the contract. What should the project manager do first?


quality management plan - CORRECT ANSWER - While developing a new smartphone,
the project team has identified a specific set of performance measurements that the phone should
meet when it is complete. The measurement looks at how fast the phone can boot up and how
fast it can shut down. Where should the project team document these measurements?


plan cost management - CORRECT ANSWER - The project manager and sponsor are
consulting with banks and other lending institutions in order to obtain funds for the project. What
process this describes these actions?


get acceptance from the project sponsor - CORRECT ANSWER - The project team has
completed a major deliverable on the game development project. The deliverable was given to
the project manager. What action should the project manager take next?

, the project is progressing (on schedule & budget) - CORRECT ANSWER - A project
manager has completed the project status report. The report states the CPI is 1.1 and the SPI is
1.14. The report was given to the project sponsor, who has become very upset about the project's
progress and has requested an immediate meeting with the project manager. What should the
project manager report in the meeting?


subject matter expert - CORRECT ANSWER - You have just been appointed the new
project manager on a product upgrade project. One person in particular at the company feels like
the project may cause them to lose their job. This person has expert knowledge of the current
product and does not feel that it needs an upgrade. What would you consider this person on your
project?


analogous estimates - CORRECT ANSWER - The project has just been initiated, and the
project sponsor calls the project manager and asks approximately when he thinks the project will
be completed. The project manager replies that they have been unable to thoroughly analyze the
work needed to complete the project and that he is not very knowledgeable about this kind of
work. The sponsor insists on receiving a high-level estimate. The project manager responds that
it will take approximately 3 months to complete the work based on his experience working on a
project very similar to this one. What technique best represents this estimate?


create a change request to correct the project - CORRECT ANSWER - While compiling
all the work performance information into the work performance report, a project manager
notices that the SPI of the project is .6 and the CPI is .7. What action should the project manager
take next on this project?


inform the stakeholder that this change request should be considered a new project - CORRECT
ANSWER - While working on a complex web design project, the manager has received a
change request from a senior stakeholder to fix a problem with the current intranet server. The
project manager has determined that this change is outside the scope of the project and is not
covered by the work listed in the project charter. What should the project manager do next?


project scope statement - CORRECT ANSWER - While planning a project, the project
manager is given many requirements that the customers would like to add to the project. Upon
further investigation, the project manager decides that a few of the requirements will not be
feasible within the limited time and cost allocated to the project. What document would best list
the requirements that will not be added to this project?

Documentinformatie

Geüpload op
17 februari 2025
Aantal pagina's
9
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden
€9,85

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
STANFORDGRADESS
4,0
(238)
Verkocht
1582
Volgers
108
Items
114633
Laatst verkocht
1 uur geleden

Echte notities, van echte studenten
Elk document op Stuvia is geschreven door een medestudent die hetzelfde vak deed. Zo leer je van iemand die het al heeft gehaald.



Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen