100% tevredenheidsgarantie Direct beschikbaar na je betaling Lees online óf als PDF Geen vaste maandelijkse kosten 4.2 TrustPilot
logo-home
Tentamen (uitwerkingen)

CSI – CDT EXAM 2024 QUESTIONS AND DETAILED ANSWERS WITH RATIONALE | 100% CORRECT ANSWERS GUARANTEED PASS

Beoordeling
-
Verkocht
-
Pagina's
45
Cijfer
A+
Geüpload op
11-03-2024
Geschreven in
2023/2024

CSI – CDT EXAM 2024 QUESTIONS AND DETAILED ANSWERS WITH RATIONALE | 100% CORRECT ANSWERS GUARANTEED PASS












Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Documentinformatie

Geüpload op
11 maart 2024
Aantal pagina's
45
Geschreven in
2023/2024
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

CSI – CDT EXAM 2024 QUESTIONS
AND DETAILED ANSWERS WITH
RATIONALE | 100% CORRECT
ANSWERS GUARANTEED PASS


Sheet keynote or reference keynote Correct Answer a notation
on a single drawing sheet

"A facility's "life cycle" includes all of the following EXCEPT:
a. Project conception
b. Financing
c. Construction
d. Facility management" Correct Answer 1. b - PRM 1.4 Life
cycle Stages: Conceptions, Delivery Method, Design,
Procurement, Construction,

What does CSI's UDS do ? what does it stand for ? Correct
Answer UDS uniform drawing system

CMa stands for... Correct Answer Construction Manager as
Advisor

"The objective of the competitive bidding process is:
a. To ensure that all qualified bidders may submit bids on public
work projects
b. To ensure that public works contracts are always awarded to
the lowest bidders
c. To ensure that the intent of the governing public laws is
maintained in the
awarding of contracts

,d. To ensure that the cost of the project is reasonable and
consistent with the
prevailing conditions in the building industry" Correct Answer 2.
d - PRM 3.4

What is included in PART 3 of SectionFormat? Correct Answer
PART 3- EXECUTION: describes field/site installation or
application, including preparatory actions and post-installation
cleaning and protection. Field/site-built assemblies and
field/site-manufactured products and systems are included.

"A unit price contract or contract portion is used when:

a. Extent of work cannot be fully determined or where actual
quantities cannot be accurately calculated.
b. Extent of work is known, but the owner desires a break-out
cost for portions of the work.
c. It is anticipated that bidders will not examine soil bearing
reports prior to submitting bid.
d. Bidding quantities of equipment.

Review: PDPG 7.1.6.2" Correct Answer "a. Extent of work
cannot be fully determined or where actual quantities cannot be
accurately calculated.

Use of unit prices, allowances and alternates should always be
limited to those items required for accurate bidding, in order to
keep bidding documents and processes as simple as possible."

"The contractual relationship governed by the Conditions of the
Contract is between:

a. Owner and contractor
b. Architect/engineer and contractor
c. Owner and Subcontractors
d. Owner, contractor, and architect/engineer

,Review: PDPG 5.5 and 11.3.9" Correct Answer "a. Owner and
contractor

The owner and the contractor are the parties to the construction
contract, hence they are subject to the Conditions of the
Contract. Yes, the duties of the architect are described in the
Conditions of the Contract, but they are governed by the
separate Owner/Architect or Owner/Engineer Agreement."

How long does a contractor required to execute corrections in
the Work after Substantial Completion? Correct Answer one
year

"Which of the following would be included in Available
Information?

a. Bid security requirements
b. Environmental Impact Statement
c. Time of completion to construct the project
d. Description of the Work

Review: PDPG 11.4.5" Correct Answer "b. Environmental
Impact Statement

Available Information is the place to provide reference
information such as this that doesn't belong in the contract. Bid
security info? In the Instructions for Procurement. Time of
Completion? It's contractual - where would you put it?
Description of Work? Name the Division 01 section where that
belongs."

"Instructions for Procurement:

a. Are used only on private projects
b. Frequently are standard industry forms
c. May include the geotechnical report as an attachment
d. Are binding upon the Contractor

, Review: PDPG 11.4.4
" Correct Answer "b. Frequently are standard industry forms

Both AIA and EJCDC offer standard printed Instructions to
Bidders forms. If necessary, a Supplementary Instructions to
Bidders can customize the Instructions to suit special project
conditions.

Did you notice? The PDPG uses the term ""Instructions for
Procurement"" as an umbrella term for both bid and negotiated
projects. MasterFormat lists both terms: Instructions for
Procurement, and the more specific documents Instructions to
Bidders or Instructions to Proposers."

"Marked-up or corrected contract drawings that indicate
changes incorporated in the Work are:

a. Contract forms
b. Closeout submittals
c. Record drawings
d. As-builts
e. Not required for private work

Review: PDPG 11.2.3.5" Correct Answer "c. Record drawings

These drawings incorporate all issued modifications and
significant field changes in scope. The term ""as-builts"" is
discouraged, as we are often unable to certify the accuracy of
actual installations and field-recorded information."

"Contractual clauses in the Conditions of the Contract:

a. Have priority over Division 01
b. Are superseded by Division 01
c. Are expanded upon by the provisions of Division 01
d. Are independent, and Division 01 provisions have no effect

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
TUTORWAC Johns Hopkins University
Bekijk profiel
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
333
Lid sinds
2 jaar
Aantal volgers
114
Documenten
3529
Laatst verkocht
1 dag geleden
TUTORWAC

BEST HOMEWORK HELP AND TUTORING ON YOUR QUIZZES AND EXAMS WITH GUARANTEE OF EXCELLENT GRADES

4,1

51 beoordelingen

5
30
4
8
3
6
2
3
1
4

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen