managed?
A
Customers
.
B
People
.
C
Benefits
.
D
Processes
.
What is the trigger for the Starting up a Project process?
A
Project Brief
.
B
Project Plan
.
C
Project mandate
.
D
Outline Business Case
.
Which is a purpose of the Business Case theme?
A Establish mechanisms to monitor and compare actual achievements
. against those planned
B
Establish methods to judge whether the ongoing project is justified
.
C
Assess and control uncertain events or situations
.
D
Describe how, when and at what cost products can be delivered
.
What role is responsible for creating a Team Plan in the Managing Product
Delivery process?
, A
Project Manager
.
B
Team Manager
.
C
Project Support
.
D
Senior User
.
The incorporation of the primary stakeholders on the project management
team supports what principle?
A
Continued business justification
.
B
Defined roles and responsibilities
.
C
Manage by stages
.
D
Learn from experience
.
Which describes risk appetite?
A
An organization's attitude towards risk-taking
.
B
Probable effect on the project delivering its objectives
.
C
Probable timeframe within which a risk may occur
.
D
Level of risk exposure that, when exceeded, triggers an exception
.
Identify the missing words in the following sentence.
If the Project Manager needs to know the results of a quality review, the [ ? ]