Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Document preview thumbnail
Voorbeeld 4 van de 60 pagina's
Tentamen (uitwerkingen)

DBIA Certification Exam Preparation — 120 Practice Questions with Answers

Document preview thumbnail
Voorbeeld 4 van de 60 pagina's

This document contains 120 DBIA certification exam preparation questions covering design-build fundamentals, procurement, contracting and pricing, risk allocation, insurance and bonds, quality management, and design development. Each multiple-choice question includes the correct answer and a rationale explaining the underlying design-build principle.

Voorbeeld van de inhoud

DBIA CERTIFICATION EXAM PREPARATION

120 Practice Questions with Answers & Rationales



Question 1
Which single characteristic most fundamentally distinguishes design-build from design-bid-
build?

A. The owner holds one contract that covers both design and construction
B. The project is always delivered faster than design-bid-build
C. A guaranteed maximum price is required on every project
D. The architect always leads the design-build entity

Correct Answer: A. The owner holds one contract that covers both design and construction

Rationale: The defining structural feature of design-build is a single contract between the owner and
one entity (the design-builder) that is responsible for both design and construction. Speed (B) is a
common benefit but not the defining feature, a GMP (C) is one of several possible commercial
structures, and either a contractor or a design professional may lead the design-build entity (D).




Question 2
Under the DBIA's 'Design-Build Done Right(R)' philosophy, which of the following is one of the
core principles?

A. Select the design-build team based solely on lowest price
B. Foster relationships based on trust and open communication
C. Finalize 100% of design documents before selecting the design-builder
D. Prohibit the design-builder from having any design staff

Correct Answer: B. Foster relationships based on trust and open communication

Rationale: Design-Build Done Right(R) principles emphasize commitment to a culture of open
communication and trust among all parties. Selecting solely on price (A) contradicts best-value
selection principles, finalizing full design before selection (C) describes design-bid-build, and design-
build entities commonly include in-house or contracted design professionals (D).

,Question 3
In a design-build project, who typically holds the single point of responsibility for both design and
construction?

A. The owner's project manager
B. The design-builder
C. The construction manager at risk
D. The owner's design consultant

Correct Answer: B. The design-builder

Rationale: Design-build creates single-point responsibility with the design-builder, who is contractually
accountable for both design and construction outcomes. This consolidation is what differentiates it
from multi-party delivery methods like CM at Risk (C), where design and construction contracts remain
separate.




Question 4
Which of the following best describes the 'design-build gap'?

A. The time between substantial completion and final completion
B. The period between contract award and notice to proceed
C. The risk created when a design professional prepares bridging documents without construction
input
D. The difference between the owner's budget and the low bid

Correct Answer: C. The risk created when a design professional prepares bridging documents
without construction input

Rationale: The design-build gap refers to the risk and inefficiency that can arise when design criteria
or bridging documents are developed without input from the builder, potentially creating conflicts,
omissions, or unrealistic expectations once construction expertise is brought in.

,Question 5
A key advantage of design-build cited by DBIA research is:

A. It eliminates the need for any owner oversight
B. It compresses schedule through overlapping design and construction activities
C. It guarantees a lower total project cost in all cases
D. It removes the need for permits

Correct Answer: B. It compresses schedule through overlapping design and construction
activities

Rationale: Because design and construction are integrated under one entity, activities can overlap
(fast-tracking), compressing overall project delivery schedules. Design-build does not eliminate owner
oversight, guarantee lower costs in every case, or remove regulatory permitting requirements.




Question 6
Which project delivery risk is most directly reduced by using design-build instead of design-bid-
build?

A. Market risk for material price escalation
B. Risk of conflicting responsibility between designer and builder
C. Risk of labor strikes
D. Risk of changes in interest rates

Correct Answer: B. Risk of conflicting responsibility between designer and builder

Rationale: Because a single entity is responsible for both design and construction, the finger-pointing
and split responsibility risk common in design-bid-build (where the designer and contractor have
separate contracts with the owner) is significantly reduced.

, Question 7
In DBIA terminology, the entity that holds the prime contract with the owner for design and
construction services is called the:

A. Design-builder
B. Owner's representative
C. Design consultant of record
D. General contractor

Correct Answer: A. Design-builder

Rationale: The design-builder is the DBIA term for the single entity under prime contract to the owner
responsible for delivering both design and construction. A general contractor (D) typically only holds a
construction contract in traditional delivery.




Question 8
Which of the following is NOT one of the commonly recognized design-build variants?

A. Contractor-led design-build
B. Architect-led design-build
C. Integrated design-build joint venture
D. Owner-led design-bid-build

Correct Answer: D. Owner-led design-bid-build

Rationale: Owner-led design-bid-build is not a design-build variant at all; it is a separate delivery
method. Contractor-led, architect-led, and joint-venture structures are all recognized design-build
organizational models.

Documentinformatie

Geüpload op
3 september 2026
Aantal pagina's
60
Geschreven in
2026/2027
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden
€12,59

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
Hosmerit
4,7
(258)
Verkocht
422
Volgers
46
Items
4622
Laatst verkocht
2 dagen geleden

Echte notities, van echte studenten
Elk document op Stuvia is geschreven door een medestudent die hetzelfde vak deed. Zo leer je van iemand die het al heeft gehaald.



Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen