An architect hires a structural engineer consultant for a new condominium project.
Five days before the design document drawings are due, the owner requests that a
rooftop garden and patio be included in the project. The structural engineer sends an
e-mail to the architect, requesting additional time and compensation for the
incorporation of the new roof modifications.


If an e-mail is an approved form of documentation according to the consultant
contract, what action should the architect take?
Forward the e-mail request with a description to the owner for review and approval.
Attach the e-mail to the owner's design document deliverables and invoice for
payment.
Reply to the e-mail asking the engineer to send their request to the architect in the
form of a letter.


Give this one a try later!

, CORRECT RESPONSE
Forward the e-mail request with a description to the owner for review and
approval.
Per the AIA B101 agreement, any adjustments to the schedule and estimate
must be submitted to the owner for approval. As e-mail has been deemed
an approved form of documentation in the architect-consultant agreement,
so the architect should not request correspondence in the form of a letter.
The architect should incorporate the engineer's communication into their
correspondence with the owner.
Topic: Contracts




Early in the construction documents phase of a project, a fire protection engineer
alerts the architect that the architect improperly classified the materials planned to be
stored in a warehouse space. The architect will need to revise the analysis of the
materials so that the fire protection engineer can correctly plan sprinkler coverage
and fire pump sizing.


What should the architect do first to respond to the lack of coordination?
Develop and submit a request for additional services.
Identify and take corrective actions to modify the project work plan.
Advise the owner of the design conditions and any impact on the schedule.


Give this one a try later!


CORRECT RESPONSE
Identify and take corrective actions to modify the project work plan.
Identifying and taking corrective action if a project is not performing
according to the project work plan is the first step the architect should take.
The architect must alert the owner of the situation but should first identify
the root cause of the error and define a path forward to resolve it prior to
the discussion with the owner.
Topic: Project Work Planning

, A university hires an architect to design a renovation and addition to a performing arts
center. The university wants to use an integrated project delivery method and contract
with a series of consultants who will each coordinate their scope of work with the
architect. The work is to be executed in multiple phases and includes the following:
Restore the original facade of the existing facility built in 1905.
Convert the existing sloped concrete floor performance hall into a new flat floor
performance space.
Renovate existing classrooms to provide new advanced audio and video laboratories.
Design a performance hall addition connected to the existing facility by an elevated
walkway.
Identify and address any AHJ or accessibility issues in the existing facility.
Who should the architect recommend the university hire before the schematic design
phase? Check the four that apply.
General contractor
Lighting designer
Geotechnical engineer
Commissioning agent
Historical preservationist
Construction manager


Give this one a try later!

Documentinformatie

Geüpload op
17 juli 2026
Aantal pagina's
17
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden
€9,30

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
CLASSROOMTEST
3,4
(10)
Verkocht
48
Volgers
3
Items
7627
Laatst verkocht
1 week geleden


Echte notities, van echte studenten
Elk document op Stuvia is geschreven door een medestudent die hetzelfde vak deed. Zo leer je van iemand die het al heeft gehaald.



Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen