VA DEQ ESC Inspector Exam EXAM Questions & Answers | Latest Already Graded A+ UPDATE 2025|2026

Document preview thumbnail
Voorbeeld 3 van de 18 pagina's

VA DEQ ESC Inspector Exam EXAM Questions & Answers | Latest Already Graded A+ UPDATE 2025|2026

Voorbeeld van de inhoud

VA DEQ ESC Inspector Exam EXAM Questions & Answers |
Latest Already Graded A+ UPDATE 2025|2026
Leave the first rating
Save




Students also studied


Flashcard sets Study guides



Erosion and Sediment Control VA DEQ ESC Inspector Exam DEQ E&S Inspector Exam DE

77 terms 104 terms 19 terms 182




kdgilmore18 Preview shaely_smith Preview whiteheadjess10 Preview




Terms in this set (104)



VESCP Virginia Erosion and Sediment Control Program


- Administered by counties/cities (must), towns (may)
- MUST BE APPROVED


Minimum Standard 1 Stabilization


permanent or temporary soil stabilization shall be applied to denuded areas
within seven days after final grade is reached on any portion of the site;
temporary soil stabilization shall be applied within seven days to denuded
areas that may not be at final grade but will remain dormant for longer than 14
days; permanent stabilization shall be applied to areas that are to be left
dormant for more than one year


Site NOT at Final Grade - stabilize in 14 days
- temporarily seed
- mulch
- permanently stabilize if dormant > 1 year




Site at Final Grade - stabilize in 7 days (recommended immediately)
- permanently or temporarily seed and mulch
- mulch/matting/straw

,Minimum Standard 2 Stock Piles, Waste and Borrow Areas


during construction, soil stock piles and borrow areas shall be stabilized or
protected with sediment trapping measures


mulch prevents erosion by protecting the surface from raindrop impact and silt
fence intercepts and detains from disturbed areas


Minimum Standard 3 Permanent Vegetation


permanent vegetation cover shall be established on denuded areas not
otherwise permanently stabilized (permanent vegetation shall not be
considered established until a ground cover is achieved that is uniform, mature
enough to survive, and will inhibit erosion there is no % associated with this)


reduce erosion and decrease sediment yield from disturbed area


this is the standard used to verify that a site is ready for release of bonds or
surety


Minimum Standard 4 First-Step Measures


Sediment basins and traps, perimeter dikes, sediment barriers and other
measures intended to trap sediment shall be constructed as a first step in any
land-disturbing activity and shall be made functional before upslope land
disturbance takes place


a certain amount of initial land disturbance may be required to provide access
for equipment to install the perimeter controls, but site clearing and grading
should be kept to a minimum until the perimeter controls are in place


intercepts and detains small amounts of sediment from disturbed areas during
construction operation to prevent sediment from leaving the site and decrease
velocity of sheet flows and low-to-moderate level channel flow


Perimeter Controls assures that sediment does not leave the perimeter of the land-disturbing area
once site clearing, grading, and construction commences


Examples: silt fences, sediment traps, sediment basins, construction entrance,
temporary diversions, diversions


Minimum Standard 5 Earthen Structure Stabilization


stabilization measures shall be applied to earthen structures such as dams,
dikes, and diversions immediately after installation


reduce erosion and sedimentation and reduce damage from sediment and
runoff to downstream or off-site areas


Minimum Standard 6 Traps and Basins


sediment traps and basins shall be designed and constructed based upon the
total drainage area (not just disturbed area) to be served by the trap or basin

, Sediment Traps minimum storage capacity shall be 134 cubic yards per acre of drainage area
and shall only control drainage areas less than 3 acres


stone outlet = trap


Sediment Basins surface runoff from disturbed areas that is comprised of flow from drainage
areas greater than or equal to 3 acres shall be controlled by a basin; minimum
storage capacity of a sediment basin shall be 134 cubic yards per acre of
drainage area; the outfall system shall, at a minimum, maintain the structural
integrity of the basin during a 25-year storm of 24-hour duration; runoff
coefficients used in runoff calculations shall correspond to a bare earth
condition or those conditions expected to exist while the sediment basin is
utilized.




Sediment Trapping Devises 1. place near the lowest drainage points of a project


2. install as a first-step measure [MS-4]


3. stabilize immediately [MS-5]


4. must include outlet protection for basins [MS-11]


Minimum Standard 7 Cut and Fill Slopes


roughening the surface of the slope decreases runoff, lowers the velocity
runoff, increases water retention, and leads to better seed germination


slopes that are found to be eroding excessively within on year of permanent
stabilization shall be provided with additional slop stabilizing measures until
the problem is corrected


Minimum Standard 8 Concentrated Runoff


shall not flow down cut or fill slopes unless contained within an adequate
temporary or permanent channel, flume or slope drain structure


outlets of these drains need outlet protection to prevent erosion from the
concentrated flow


size of pipe depends on drainage area


temporarily conduct concentrated stormwater runoff safely down the face of a
cut or fill slope without causing erosion on or below the slope

Documentinformatie

Geüpload op
13 juni 2026
Aantal pagina's
18
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden
Gratis
Downloaden

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
Studiies
5,0
(2)
Verkocht
4557
Volgers
1
Items
1585
Laatst verkocht
7 uur geleden

Echte notities, van echte studenten
Elk document op Stuvia is geschreven door een medestudent die hetzelfde vak deed. Zo leer je van iemand die het al heeft gehaald.



Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen