OPSM 4820 Exam 3 Questions With New Update Solutions /. ____________________ concerns execution of material plans. a. ERP b. MRP c. MPC d. PAC e. "a" and "d" - Answer-d. PAC /.In purchasing, ____________ is seen as a professional activity where information networks, relationships, terms, and conditions are established with vendor companies outside of production activity control, while release of individual orders and follow-up activities are a part of production activity control. a. warehousing b. inventory c. procurement d. "a" and "b" e. none - Answer-c. procurement /._____________ includes where things are, notification of operational completions, count verifications, order closeout and disposition, and accounting data. c. feedback b. status information d. "a" and "b" a. warning signals e. none - Answer-b. status information /._____________ help flag inadequacies in material and capacity plans e. none d. "a" and "b" c. feedback a. warning signals b. status information - Answer-a. warning signals /.Formal systems for shop-floor control are largely unnecessary under ______. Release of orders is still part of PAC, but the typical "shop order" with associated paperwork isn't maintained. e. PAC d. MPC b. ERP c. JIT a. MRP - Answer-c. JIT /.Vendor scheduling under __________ can be a bit more complex than shop-floor control, but if the relationship with the vendors is good, differences are very small. e. PAC b. ERP c. JIT a. MRP d. MPC - Answer-c. JIT /.The primary __________ objective is managing the materials flow to meet _________ plans. a. PAC, MPC b. MPC, PAC c. PAC, MRP d. MRP, PAC e. none - Answer-a. PAC, MPC /.The choice of objectives for ___________ reflects the firm's position vis-à-vis its competitors, customers, and vendors. e. JIT d. MRP b. APC a. PAC c. MPC - Answer-a. PAC /._________ is an approach to shop-floor control. b. priority sequencing rules c. theory of constraints scheduling a. gantt charts d. all e. none - Answer-d. all - gantt charts - theory of constraints scheduling - priority sequencing rules /.Reducing ________ means shorter lead time and, therefore, reduced work-in-process inventory. a. demand d. "a" and "c" e. none c. inventory b. queue time - Answer-b. queue time /.__________ show a schedule in production activity control techniques. c. bar charts b. priority sequencing rules d. "a" and "c" e. none a. gantt charts - Answer-d. "a" and "c" - gantt charts - bar charts /.________________ determine which job to run next at a work center in production activity control techniques. d. "a" and "c" c. bar charts e. none a. gantt charts b. priority sequencing rules - Answer-b. priority sequencing rules /.In an ____________ system, each shop order would be a scheduled receipt for the part. As such, the scheduled receipt has a due date. c. JIT d. MPC e. TOC b. ERP a. MRP - Answer-a. MRP /.Theory of constraints (TOC) scheduling systems were viewed as a replacement of an integrated MPC system. b. ERP a. MRP e. TOC d. MPC c. JIT - Answer-d. MPC /.Any resource whose capacity is equal to or less than the required demand is referred to as a _____________ . d. "a" and "c" a. bottleneck c. constraint e. none b. limited - Answer-a. bottleneck /.The objective of __________ scheduling is to maximize throughput. e. TOC d. MPC c. JIT b. ERP a. MRP - Answer-e. TOC

Voorbeeld van de inhoud

OPSM 4820 Exam 3 Questions With
New Update Solutions
/. ____________________ concerns execution of material plans.
a. ERP
b. MRP
c. MPC
d. PAC
e. "a" and "d" - Answer-d. PAC

/.In purchasing, ____________ is seen as a professional activity where information
networks, relationships, terms, and conditions are established with vendor companies
outside of production activity control, while release of individual orders and follow-up
activities are a part of production activity control.
a. warehousing
b. inventory
c. procurement
d. "a" and "b"
e. none - Answer-c. procurement

/._____________ includes where things are, notification of operational completions,
count verifications, order closeout and disposition, and accounting data.
c. feedback
b. status information
d. "a" and "b"
a. warning signals
e. none - Answer-b. status information

/._____________ help flag inadequacies in material and capacity plans
e. none
d. "a" and "b"
c. feedback
a. warning signals
b. status information - Answer-a. warning signals

/.Formal systems for shop-floor control are largely unnecessary under ______. Release
of orders is still part of PAC, but the typical "shop order" with associated paperwork isn't
maintained.
e. PAC
d. MPC
b. ERP
c. JIT
a. MRP - Answer-c. JIT

,/.Vendor scheduling under __________ can be a bit more complex than shop-floor
control, but if the relationship with the vendors is good, differences are very small.
e. PAC
b. ERP
c. JIT
a. MRP
d. MPC - Answer-c. JIT

/.The primary __________ objective is managing the materials flow to meet _________
plans.
a. PAC, MPC
b. MPC, PAC
c. PAC, MRP
d. MRP, PAC
e. none - Answer-a. PAC, MPC

/.The choice of objectives for ___________ reflects the firm's position vis-à-vis its
competitors, customers, and vendors.
e. JIT
d. MRP
b. APC
a. PAC
c. MPC - Answer-a. PAC

/._________ is an approach to shop-floor control.
b. priority sequencing rules
c. theory of constraints scheduling
a. gantt charts
d. all
e. none - Answer-d. all
- gantt charts
- theory of constraints scheduling
- priority sequencing rules

/.Reducing ________ means shorter lead time and, therefore, reduced work-in-process
inventory.
a. demand
d. "a" and "c"
e. none
c. inventory
b. queue time - Answer-b. queue time

/.__________ show a schedule in production activity control techniques.
c. bar charts
b. priority sequencing rules

, d. "a" and "c"
e. none
a. gantt charts - Answer-d. "a" and "c"
- gantt charts
- bar charts

/.________________ determine which job to run next at a work center in production
activity control techniques.
d. "a" and "c"
c. bar charts
e. none
a. gantt charts
b. priority sequencing rules - Answer-b. priority sequencing rules

/.In an ____________ system, each shop order would be a scheduled receipt for the
part. As such, the scheduled receipt has a due date.
c. JIT
d. MPC
e. TOC
b. ERP
a. MRP - Answer-a. MRP

/.Theory of constraints (TOC) scheduling systems were viewed as a replacement of an
integrated MPC system.
b. ERP
a. MRP
e. TOC
d. MPC
c. JIT - Answer-d. MPC

/.Any resource whose capacity is equal to or less than the required demand is referred
to as a _____________ .
d. "a" and "c"
a. bottleneck
c. constraint
e. none
b. limited - Answer-a. bottleneck

/.The objective of __________ scheduling is to maximize throughput.
e. TOC
d. MPC
c. JIT
b. ERP
a. MRP - Answer-e. TOC

Documentinformatie

Geüpload op
22 april 2026
Aantal pagina's
17
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden
€13,76

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
Brainariam
3,3
(27)
Verkocht
156
Volgers
7
Items
8404
Laatst verkocht
2 weken geleden

Echte notities, van echte studenten
Elk document op Stuvia is geschreven door een medestudent die hetzelfde vak deed. Zo leer je van iemand die het al heeft gehaald.



Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen