1


SOS NERC Prep - RElIABILITY Exam
Questions with Correct Answers | Updated
(100% Correct Answers)
The Reliability Coordinator just informed you of a slow time error
correction which will begin at the top of the next hour. Your EMS
system will not let you change your scheduled frequency. Your
Frequency Bias Setting is -100 MW/.1Hz. What action should you
take?

A) Increase Net Interchange Schedule by 20 MWs.

B) Inform the Reliability Coordinator that you cannot participate in
the time error correction.

C) Decrease Net Interchange Schedule by 20 MWs.

D) Increase Net Interchange Schedule by 10 MWs. Answer: A)
Increase Net Interchange Schedule by 20 MWs.

A Balancing Authority has a sudden loss of a large block of load in
its area. This loss will be seen instantaneously in the change of
which of the following values?

1. Actual Net Interchange

2. Scheduled Frequency


© 2025 All rights reserved

,2
3. Scheduled Net Interchange

4. Area Control Error

A) 4 only

B) 1 & 3

C) 1 & 4

D) 3 & 4 Answer: C) 1 & 4

Metered Data included in the calculation of ACE are: dynamic
schedules, pseudo ties, actual frequency, and all __________.

A) Tie lines readings

B) Generators output

C) Scheduled frequency indications

D) Transformer load Answer: A) Tie lines readings

Balancing Authority A is currently reading a system frequency of
60.00 Hz. Its Net Actual Interchange is +100 MW and its Net
Scheduled Interchange is +200 MW. If Balancing Authority A's
frequency bias setting is 100 MW/0.1 Hz, what is ACE?

A) -100



© 2025 All rights reserved

,3
B) 0

C) 10

D) 100 Answer: A) -100

A Balancing Authority has a Net Interchange Schedule of -250 MWs
from 1200 to 1600 on a summer day. The Net Interchange Actual
for those same hours respectively were -230 MW, -275 MW, -250
MW and -270 MW. What was the Balancing Authority's Inadvertent
Interchange for the 4-hour period?

A) 6 MWs out

B) 25 MWs in

C) 25 MWs out

D) 6 MWs in Answer: B) 25 MWs in

For the ACE equation to work properly, dynamic schedules, pseudo
ties, frequency, and all ________________ must be metered.

A) Generation

B) Communications

C) Transformers

D) Tie lines Answer: D) Tie lines

© 2025 All rights reserved

, 4
If the frequency bias setting is set to a less negative value than the
frequency response of a Balancing Authority and a frequency
increase is caused by a sudden loss of load in an external balancing
area, what will be the result?

A) The ACE will be zero and will take no AGC action

B) The ACE will be a negative value and AGC will increase
generation

C) The ACE will be a positive value and AGC will lower generation

D)This will not affect the ACE Answer: B) The ACE will be a negative
value and AGC will increase generation

If the frequency bias setting is less negative than the frequency
response of a Balancing Authority and a frequency decline is caused
by a sudden loss of generation in an external balancing area, what
will be the result?

A) The ACE will be a negative value and AGC will increase
generation.

B) This will not affect the ACE.

C) The ACE will be a positive value and AGC will lower generation.

D) The ACE will be zero and will take no AGC action. Answer: C)
The ACE will be a positive value and AGC will lower generation.

© 2025 All rights reserved

Documentinformatie

Geüpload op
17 januari 2026
Aantal pagina's
98
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden
€16,85

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
Passit
3,5
(23)
Verkocht
128
Volgers
6
Items
14482
Laatst verkocht
2 weken geleden

Echte notities, van echte studenten
Elk document op Stuvia is geschreven door een medestudent die hetzelfde vak deed. Zo leer je van iemand die het al heeft gehaald.



Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen