(5.2) Job Safety Analysis (JSA)_Hazard Recognition: Correct
Answers a) Job Site
b) Environmental
c) Site-specific Hazards
d) Climatic and Other Work Condition Hazards
e) Materials and Material Handling
f) Work Task Review
g) Emergency Conditions
1) SPCC:
2) SSPC: Correct Answers 1) Spill prevention, control, &
containment
2) The Society for Protective Coatings
5.10 Excavation, Trenching, and Boring Safety Correct
Answers OSHA 1926 Subpart P
5.10.4 Use of Explosive for Excavation Correct Answers
OSHA 1910.109, OSHA 1926.900 to 1926.914, and 49 CFR
177.835
5.11 Confined Space Entry Requirements Correct Answers
OSHA 1910.146
5.11.2 Rescue and Emergency Services Correct Answers
OSHA 1910.146(k)
, 5.12 Atmospheric Testing
OSHA 1910.146 Appendices B and D Correct Answers —
gas/vapor/mist/dust in excess of LFL.
— Oxygen < 19.5% or > 23.5%.
— PELs (see OSHA 1910.1000).
— other toxic atmospheric conditions
5.16.2 Transportation, Use, and Storage of Flammable and
Combustible Liquids Correct Answers OSHA 1910.106 and
1926.152
5.16.3 Transportation, Handling, Labeling, Storage, and Use of
Compressed Gases Correct Answers
5.16.4.2 Tools (Tool Safety) Correct Answers — use the right
tool for the job;
— tool condition;
— correct use of the tool;
— safety features i.e. guards & welding hoods are in place;
— use protective equipment, including: hard hats, facial shields,
PPE as well as suitable clothing for the type of work.
5.3 Personal Protective Equipment (PPE): Correct Answers
Typically, PPE for pipeline construction includes but is not
limited to approved eye, head, foot, hand, and
hearing protection; safety apparel; respiratory devices; and
various protective shields.
5.3.6 Hearing Protection is required when noise level: Correct
Answers >85 dbA per 8hr