Radeon Homes Microsoft Office 365 Project Plan
Phase Project Week Milestones
Phase 1: Planning Week 1 Project kickoff with Microsoft consulting team
2 Weeks Existing infrastructure inventory complete
Week 2
40 hours Assign projectManager
Configuration tasks to PM team
setup andlicenses
& 150 consultin
Phase 2: Execution Week 3 migrated
3 Weeks Week 4 Remaining 150 licenses migrated
80 hours Week 5 Decommission legacy applications, servers &
Monitor O365 usage and confirm everything i
Phase 3: Monitoring Week 6 Final decommission of remaining legacy appl
1 Week servers and software
40 hours Consulting team to begin training for Radeon
Phase 4: Project Closure Final documentation to be provided to leader
Week 7
1 Week Continued consulting team training for Radeo
40 hours employees
Phase Project Week Milestones
Phase 1: Planning Week 1 Project kickoff with Microsoft consulting team
2 Weeks Existing infrastructure inventory complete
Week 2
40 hours Assign projectManager
Configuration tasks to PM team
setup andlicenses
& 150 consultin
Phase 2: Execution Week 3 migrated
3 Weeks Week 4 Remaining 150 licenses migrated
80 hours Week 5 Decommission legacy applications, servers &
Monitor O365 usage and confirm everything i
Phase 3: Monitoring Week 6 Final decommission of remaining legacy appl
1 Week servers and software
40 hours Consulting team to begin training for Radeon
Phase 4: Project Closure Final documentation to be provided to leader
Week 7
1 Week Continued consulting team training for Radeo
40 hours employees